Previous Page Table of Contents


ANNEX 1

SCHEDULE OF WORK

 Briefing in Rome with the Project Manager
  5.11.84Arrival in Nairobi
  9.11.84Arrival in Malindi, discussions with FAO and Resident Representative's in visit to the project
12.11.84Meeting with project staff
16.11.84Departure on leave of the Project Manager
19.11.84Nairobi: visit to the FAO Representative's office
- to the Fisheries Department headquarters
- to the Soil Survey of Kenya Department
- to investors
21.11.84Return to the project
22.–24.11.84Visit of the Tourism and Wildlife Accountancy Mission
  2.–5.12.84Visit of the Site Survey Mission
10.12.84Nairobi: report - to the FAO Representative's office
- to the UNDP headquarters
- to the Fisheries Department headquarters
meeting with investors
13.12.84Return to Rome
14.12.84Report to FAO Headquarters, Rome

LIST OF PERSONS MET

Government of Kenya

United Nations

Private Industry

PERSONNEL ATTACHED TO THE PROJECT

FAO STAFF

Note: previously there were 2 biologist/associate experts until early 1984 and one fishfarm manager throughout 1983

KENYA STAFF

total in Malindi      13
total in Ngomeni   20
one on fellowship

TABLE 1: PRODUCTION RESULTS

 1234567
1YEAR/No/PdDate St./HvGROW.DENS/m2Prod(kg)kg/haMk W. g
281/1/315/6_14/10113>7        95.591.831.4
381/2/314/12_17/393>3,5    167160.65.5
482/1/211/1_15/4941.93730.836.1
582/2/112/1_28/41062.154.54511.8
682/3/313/4_14/7923.5199191.37.3
782/4/2Exp.     
882/5/1Exp.     
982/6/319/8_19/11914278267.35.7
1082/7/53/9_6/12933.8277174.2.5.3
1182/8/217/9_17/12903182151.75.3
1282/9/420/9_4/11054163105.84
1382/10/15/10_10/1964182165.55.9
1482/11/3Exp.     
1582/12/630/12_30/389111682.869.2
1683/1/514/1_18/492226416610.8
1783/2/428/1_29/4901.5181117.56.9
1883/3/314/2_18/5892.21291247
1983/4/228/2_2/6921.7208173.310.8
2083/5/114/3_15/6931.32724.552.2
2183/6/627/4_28/71001.56143.573.5
2283/7/512/5_11/8901.3198124.57.6
2383/8/425/5_24/8901.8180116.910.3
2483/9/39/6_23/911669894.235
2583/10/225/8_29/11961.7236196.710
2683/11/16/9_3/11181.810292.734.7
2783/12/622/9_29/129825438.577.5
2883/13/55/10_13/11017.2533335.27.2
2983/14/410/10_24/1943386250.610.8
3083/15/324/10_8/21081.4141135.68.9
3183/16/2_22/39321621357.3
3284/1/1_17/41041.85449.095.1
3384/2/6_26_4912.5275196.47.7
3484/3/?Exp.     
3584/4/5-13/6984245154.111.3
3684/5/4_19/71193.2312202.67.6
3784/6/319/3_19/71003174167.36.8
3884/7/24/4_13/7782199165.89.3
3984/8/NPExp.     
4084/9/130/4_17/7771.26155.455.1
4184/10/6Exp.     
4284/11/420/7_6/111097356231.29
4384/12/21/8_31/10922.2209174.29

Column

1      Year/culture serial number/pond code number
2      Date of stocking/date of harvest
3      Duration of grow-out (days)
4      Density of shrimp fry stocked (number/m2)
5      Final production (weight in kg)
6      Production rate: weight/hectare
7      Mean weight of individual shrimp (gr)

Exp. experimental cycle - no production data

TABLE 2: AVERAGE PRODUCTION BY POND

 123
  kgkg/ha
 Av. Pd No 17265.5
 Av. Pd No 2176147
 Av. Pd No 3160154
 Av. Pd No 4263171
 Av. Pd No 5303191
 Av. Pd No 68460
 Av. / ha 142
 Av. W. 7.2g

kg = average weight of shrimp production per harvest period approx. 90 d

TABLE 3 : GROWTH CURVES

Trial No                              Pond No                              Area                             

Date of Stocking                                

Date of harvesting                                   No of days                                

ESTIMATED NOTotal95%per ha
1.Stocked   
(a) all species                                                                        
(b) P. indicus                                                                        
2.Harvested                                                                        
(marketable)                                                                        

HARVESTKg%Kg per ha
PrawnsLarge                                                                        
 Medium                                                                        
 Sub Total                                                                        
 Small                                                                        
 Grand Total                                                                        
Crabs (kg)                                                 
Fish (kg)                                                 

AVERAGE SIZESAve (g)Range (g)
Large                                                
Medium                                                
Overall (marketable)                                                
Small                                                

INFORMATION TAKEN IN EACH WATER CHANGES IN ALL PONDS198        

PrecipitationDATE BEFORE DRAININGDATE AFTER DRAINING
- - - - - - mm
TIDE - - - - -P1P2P3P4NPP1P2P3P4NP
Time          
Water level (cm)          
Temperature °C          
pH          
Salinity: Station and bottle no:          
D.O. (Dissolved Oxygen)          
Transparence (cm)          
Closing Time          
New Level          
REMARKS          

BIOLOGICAL DATA (SAMPLING/STOCKING)

DATE                          POND                          STATION                         

GEAR                                                               SAMPLE NO                         

REMARKS                                                                                                                         

SpeciesLength (cm)NumberTotal weight (g)Average weight (g)%
P. indicus     
"
     
"
     
"
     
"
     
"
     
"
     
P. monodon     
"
     
"
     
M. monoceros     
"
     
"
     
Caridaeids     
Acetes sp     
TOTAL     

1 SAMPLE OF PRAWNS FROM POND                                                 

HARVEST/GROWTH                                                                          SPECIES                                                 

DATE COLLECTED                                                                         

INDIVIDUAL WEIGHT IN GRAMS

NOWEIGHTNOWEIGHTNOWEIGHTNOWEIGHT
--------
--------
--------
--------
--------
--------
--------
--------
--------
--------
--------
--------
--------
--------
--------
--------
--------
--------
--------
--------
--------
--------
--------

ANNEXE 2

Proposals for improvement of the pond gate

FARMING PROCEDURE NO. 1: MR. PADLAN'S RECOMMENDATIONS

RECOMMENDATIONS FOR HASTENING DEVELOPMENT OF GELATINOUS MUD AT NGOMENI PILOT FISH FARM

A. Slightly acid to slightly alkaline pond soils (pH 6.5–7.5)

  1. Dry pond bottom for 7 to 10 days
  2. Let in water through fine mesh bag net screen to a depth of 60 cm minimum, 1.0 m maximum
  3. Fertilize immediately with chicken manure at 150 kg/ha or raw cow dung at 300 kg/ha plus ammonium phosphate (16-20-0 or 20-20-0, NPK) at 25 kg/ha.
  4. If chicken manure is used, apply weekly thereafter at 100 kg/ha and ammonium phosphate at 20 kg/ha. Chicken manure should be soaked one night before and applied evenly and simultaneously with ammonium phosphate.
  5. If raw cow dung is used, apply at 60 to 100 kg/ha every other day, or 200 to 300 kg/ha every week plus 20 kg/ha of ammonium phosphate at weekly intervals.
  6. Continue application of fertilizers for three months.
  7. Pond may be stocked with mullet fingerlings (0.5 to 2 g) up to 10 000/ha 1 to utilize the space and time, but institute aeration immediately, or apply hydrated lime up to 200 kg/ha evenly over the water surface if O2 deficiency symptons (fish bobbing on surface before sunrise) occur or allow new water if tide conditions permit.
  8. Drain pond and dry.

B. Acidic soils (pH 5.0 to 6.0)

  1. Before levelling work, apply 1.5 tons of agricultural lime/ha over the pond bottom. Let in 5 cm in water. 2
  2. Level pond bottom, loosening soil to soft consistency up to 15 cm during the process.
  3. Drain, apply 1.5 tons of agricultural lime/ha over the entire pond.
  4. Proceed as in A.

C. Acidic soils (pH 4 to 4.5)

  1. Proceeds as in B, steps 1 and 2, but apply agricultural lime at double the rate.
  2. Allow about 15 to 20 cm of water and let it stay for 2 weeks. At the end of this period, test water pH just before sunrise.
  3. If pH is lower than 5.5, drain pond, dry for 2 weeks and repeat step 2.
  4. Repeat step 3 until pH reaches 5.5.

1 If stocked with fish, pond salinity should not be allowed to exceed 45 ppt. When salinity goes beyond this level, initiate partial water exchange 1 or 2 days before the next fertilization schedule. Limit carrying capacity of pond to 600 kg/ha at one time. Make partial harvest of 100 to 200 kg/ha when this is reached. Confine fish in supply canal for 2–3 days to get rid of strong smell if they are intended for the market. Harvest or transfer fish to another area for further growing.

2 Consultants' additional recommendations to Mr. Padlan's procedures.

CULTURE OF LABLAB AFTER FORMATION OF 5–10 CM LAYER OF HYDROPHILIC MUD

A. January to March (before long rains)

  1. Drain pond and dry until moisture content of soil is about 20%. Without moisture tester, this can be determined by walking over pond bottom. Drying is complete if standing on one leg, one does not sink more than 1 cm. Care should be taken not to over dry point of dessication of surface layer.
  2. Distribute chicken manure in heaps at regular interval to conform to application at 2 t/ha, air dry weight.
  3. Allow water. On a well levelled pond, this should be an average depth of 5 to 7 cm over platform.
  4. Distribute the chicken manure evenly after it has soaked.
  5. Allow water to dry by evaporation.
  6. Allow pond bottom to dry until 20% moisture content is attained again.
  7. Let in new water to an average depth of 7–8 cm.
  8. After 3 days, when a thin layer of lablab has developed, apply ammonium phosphate (16-20-0 or 20-20-0 NPK) at 25 kg/ha.
  9. After 2 weeks, raise water gradually to 15 cm at not more than 2 cm per day. Then apply ammonium phosphate at 10 g/m3 of water.
  10. Continue raising water every spring tide until 40 cm depth is attained. By this time, rains will have started to fall, reducing salinity to suitable levels for stocking.
  11. Apply ammonium phosphate weekly thereafter at same rate as in 9.

B. August to September

  1. Drain and dry pond last rain to 20% moisture content.
  2. Allow water to a depth of 7 to 10 cm
  3. After 3 days, fertilize with diammonium phosphate (18-46-0) at 50 kg/ha.
  4. Raise water gradually to 40 cm.
  5. Apply diammonium at about 8 g/m3 at weekly intervals.

Note: In all operations A and B, pond may be stocked as soon as water has reached a depth of 25 to 30 cm. Ensure proper acclimatization measures, however, before releasing fish into the pond. Shrimps may be stocked if salinity is within growing range.

FARMING PROCEDURE NO. 2: COUNTING PROCEDURE A

FARMING PROCEDURE NO. 3: COUNTING PROCEDURE B

FARMING PROCEDURE NO. 4: SAMPLING METHODOLOGY

DAILY OPERATION DATA

The form is to be filled everyday; it must give a detailed report of what is happening in each pond.

Environmental data

Weather: it can be reported as sunny, cloudy or rainy.

Water exchange

The water exchange will be done automatically as soon as an improved gate design will be put in service. The water exchange will be noted as + on the day of exchange and O when there will be no exchange. The level must be recorded just after closing the gate and just before opening it. The salinity must be read with the refractometer every other day and just before opening the gate.

Lablab

The pond manager will appreciate the growth of lablab as none, little, normal or excess.

Comments

In this column will be specified the activity developed every day in each pond such as drying, elimination of crabs, fertilization with the type of fertilizer and the amount used in kg, preparation of lablab, stocking with the exact number, sampling, harvesting, etc.

Any additional intervention or unusual observations must be specified such as an anormal colour of the soil or the water, problems at the gate or maintenance of the pond (tilling, reinforcement of the dike, etc.).

DAILY OPERATION DATA

DATE  
ENVIRONMENT  
 Tide:Precipitation:
 Weather:Salinity:
 Gate Water Temp.: 

POND MANAGEMENT DATA

 WatersTemps.Sal.D.O.DiskLab labComments
Exch.LevelMin.Max.
1         
2         
3         
4         
5         
6         
7         
8         
9         
NP         

  OPERATIONAL EXPENSESOPERATION NO: 
Date    Total
 Pond and Lablab preparation. 
 No. of workerstime (hour)activity  
      
      
      
 Fertilizers typecost/kgQuantityTransport 
 Stocking    
  No. of juvenilesNo. of workersTimeExtra costs 
      
      
 Grow out phase    
 No. of workerstime (hours)activity  
      
      
      
      
      
 Harvest    
  No. of workerstimeactivityextra 
      
      

For administration use only

Staff and administration pro rata expenses.

OPERATION NO

POPULATION RECORD DATA

 PondArea
STOCKING DATE  
Total
  
Indicus
Per ha 

GROW OUT
Sampling date
    
Weight (g)    
     
     
     
     
     
     

HARVEST DATE
 J3210SmallCrabFish
kg        
%        

Total marketablePer ha
Total producedPer ha
Average weight 
Nof of days 
Growth per week 

OBSERVATIONS:

OPERATION NO

POND RECORD DATA

Proceeding Harvest Date Pond NoArea
POND PREPARATION    
FromToComments  
     
LABLAB PREPARATION    
FromToComments  

PONDS PARAMETERS
Date
From
ToWater Exch.Final LevelAve MinTemp MaxSalinitySecchiD.O.Lab LabComments
           

OBSERVATIONS:


Previous Page Top of Page