4 WORK PLAN FOR FIRST FOUR MONTHS IMPLEMENTATION OF THE PROJECT

OUTPUTACTIVITYMONTH 1MONTH 2MONTH 3MONTH 4
1.Training fish farm managers overseas early 89.    
  1.1.Selection of candidates (4)====================  
  1.2.Identification appropriate institution============================== 
  1.3.Scheduling overseas training course========================================
2.Construction of new Fishfry Production Centres.    
  2.1. Identification of sites (Busia or Siaya, Kisii, Nyamira)============================== 
  2.2. Study of the sites: geologist survey, independant consultant study and advices  ====================
  2.3. Selection of sites   ==========
  2.4. Mapping of selected sites   ==========
3.Maintenance of operational FPCs.    
  3.1. Control & management of the 4 FPCs========================================
  3.2. Purchases of expendable items for operation of FPCs========================================
  3.3. Purchases of non-expendable items as outlined in the Project Document========================================
  3.4.Hiring of casual labour as may be required from time to time========================================
  3.5.Undertaking of cost-benefit analysis trials on various culture systems========================================
  3.6.Production of fingerlings from FPCs========================================
  3.7.Achievement of Chwele FPC============================== 
  3.8.Stocking of Chwele FPC   ==========
  3.9.Maintenance and repairs operating FPCs Kibos, Rongo, Borabu========================================
  3.10.Draining and renewing broostock all FPCs (from Lake Victoria)  ====================
4.Equipment: FAO HQs purchases.    
  4.1. Definition of the required equipment==========   
  4.2. Ordering of equipment through FAO HQ====================  
5.Extension services.    
  5.1. Creation of more public awareness========================================
  5.2. Rehabilitation of fishfarmers ponds========================================
  5.3. Collection and up-dating ponds data========================================
  5.4. Repair DFCs motorcycles and FFEs bicycles====================  
  5.5. Redistribute and balance the duties of FFEs==========   
  5.6. Fingerlings delivering to farmers========================================
  5.7. Survey “unknown status” ponds========================================
6.Credit Revolving Fund.    
  6.1. Scrutiny of the LBDA proposed modus operanti====================  
  6.2. Economics consultancy (independent consultant: FAO....)  ========== 
  6.3. Circulation of the amended proposal to the parties concerned ==================== 
  6.4. Arrangements for establishment of the scheme   ==========
7.Construction of the Project offices.    
  7.1.Preparation of bill of quantity==========   
  7.2.Preparation of tender documents==========   
  7.3.Communicate to FAO/UNDP/BSF ==========  
  7.4.Awarding tenders ==============================
8.Steering-consultative Committee    
  8.1.Formation of the Committee====================  
  8.2.Briefing of the committee members on Project activities ==============================
9.Recruitment of National professional    
  9.1.Recruitment of Administrative Assistant as outlined in the Project Document==========   
10.Consultancy: Fish-farming Produce Marketing    
  10.1.Supervision of the consultant's work====================  