Itinerary | |
16.11.86 | Depart for Rome (James Muir) |
17.11.86 | Depart for Rome (Luc Berg) Arrival in Rome,.briefing |
18.11.86 | Collect visa, tickets, etc. Depart for Tripoli. |
19.11.86 | Meeting with Mr. Asplund, UNDP Res. Rep., Dr. El Zweik, FAO Coordinator, Mr. Abofela, Project Manager designate. Travel to Zawia to site. Preliminary design concepts |
20.11.86 | Discussions, site development, Dr. El Zweik, Mr. Abofela; meeting with MEMCO, engineering contractors staff. preparation of Outline plans, further details |
21.11.86 | Detailed design,specifications. Discussions with MEMCO. staff at Zawia re Layout, construction-, use of site. Report preparation. |
22.11.86 | Report preparation, design. Discussions with Mr. Asplund, Dr.EL Zweik, representatives of MEMCO |
23.11.86 | Report preparation, final designs, costings, timetables |
24.11.86 | Discussions on project design, implementation with Mr.Abofela, arrangements for further work. Depart for Rome. |
25.11.86 | Discussions on project implementation, debriefing, FAO Rome. Preparation of follow up/continuation work |
26.11.86 | Further document work, etc. |
27.11.86 | Depart for UK |
Persons met
Gunnar Asplund, UNDP Res. Rep., Tripoli
Dr. ALi EL Zweik, FAO Project Coordinator, Zawia
Jalal Abofela, Project Manager designate, Zawia
Mr. Husni, Governor of the People's Committee of Zawia
MEMCO: Managing Director and local Director