STANDARD PLANS FOR A SMALL ABATTOIR AND MEAT MARKET
SECTION 3
SCHEDULE OF QUANTITIES

MODULAR SMALL ABATTOIR
AND MEAT MARKET
GENERAL NOTES TO THE SCHEDULE OF QUANTITIES

The schedule of quantities has been prepared in sections, as shown on the main summary sheet, to enable the various options available, to be included/excluded, as the need arises.

There are options within the various sections, and these have been measured in such a way that inclusion/exclusion can be easily identified.

Where aspects of work relate to a particular section they have generally been measured within that section.

Refer to the Site Works Section for exclusions under this section.

The Preliminaries Section is to be read in conjunction with the whole project.

MODULAR SMALL ABATTOIR
AND MEAT MARKET
MAIN SUMMARY

  $
Slaughter House  
Lairage  
Tripery  
Cutting and Processing  
Chiller  
Boiler  
Drainage and Waste  
Siteworks  
Meat Market  
Equipment  
Contractors Margin  
 TENDER AMOUNT 

MODULAR SMALL ABATTOIR
AND MEAT MARKET
SLAUGHTER HOUSE
SUMMARY

  $
Preliminaries  
Excavation  
Concrete  
Reinforcing Steel  
Concrete Masonry/Brickwork  
Metal Work  
Carpentry  
End Roof Frames  
Roof Structure  
Option A Timber  
Option B Welded Steelwork  
Option C Bolted Steelwork  
Lifting Beam  
Option A Timber  
Option B Steel  
Doors  
Option A Timber Frame  
Option B Steel Frame  
Roof Cladding  
Plumbing  
Solid Plaster  
Electrical  
TOTAL CARRIED TO MAIN SUMMARY 

PRELIMINARIES

This schedule of quantities is to be read in conjunction with the drawings and specification.

This preliminaries section is to be used for all the production modules, service modules and meat market.

The schedule has been prepared on the basis of a flat site without the need for hardfill.

 QUANTITYUNIT UNIT RATETOTAL PRICE
Tenderers shall visit the site and make themselves fully conversant with all factors which may affect the tender price and allow accordingly.1SUM  
Allow to give all notices obtain all fees and levies to the Government and/or Local Authorities having jurisdiction over the works.1SUM  
Allow to comply with all Acts of Parliament and Regulations made thereunder applicable to the works.1SUM  
Allow to provide fencing, boardings, lighting and a nightwatchman all as required for the protection of the works.1SUM  
Allow for all temporary scaffolding as required to construct the works.1SUM  
Allow to set out the works.1SUM  
Allow to provide temporary drainage to ensure that the site does not flood during heavy rainfall.1SUM  
Allow for all other site establishment and associated costs necessary to carry out the works1SUM  
TOTAL CARRIED TO SUMMARY 

EXCAVATION
 QUANTITYUNIT UNIT RATE TOTALPRICE
Clear site of all vegetation50M2  
Excavate down to sand level2.4M3  
Excavate for footings1.3M3  
Extra value for forming batter17.8M  
Backfill to foundations0.7M3  
Remove surplus spoil3M3  
50mm blinding sand under slab16.6M2  
SUMP    
Excavate for sump0.22M3  
Backfill0.11M3  
Remove surplus spoil0.11M3  
TOTAL CARRIED TO SUMMARY 

CONCRETE

Rates for concrete shall include for vibrating and for placing around rod and mesh reinforcement.

Rates for formwork shall include for all bracing and support, nails, bolts, ties and the like and all labours in erecting, striking and removing.

Rates, for concrete shall include for all screeds and screeding.

 QUANTITYUNIT UNIT RATE TOTAL PRICE
FOUNDATIONS AND SLAB    
25MPa Concrete3.6M3  
Formwork to last5.5M2  
Formwork 0–100mm wide to form channel12M  
Form slab to falls20M2  
Provide broom finish to slab20M2  
0.25mm thick polythene damp-proof sheet22M2  
Form construction joint to floor slab. Include for 10 × 10 poly sulphide sealant4.2M  
COLUMNS    
25MPa concrete1.3M3  
Formwork to sides of last 200mm wide133M  
Take delivery and cast in 50 × 50 × 5 L to top of columns8No  
Supply and cast in 150mm into concrete M12 bolts8No  
LINTELS    
25MPa concrete0.7M3  
Formwork to sides of last 200mm wide36M  
Ditto to soffit of lintels ditto18M  
Take delivery and cast 125mm into concrete 50 × 6 m.s. flat6No  
Supply and cast in 175mm long M10 bolts96No  
Ditto 140mm long M12 bolts29No  
DOOR PILLARS    
25MPa concrete0.4M3  
Formwork to sides of last 0–100 wide31M  
Ditto 200–300 wide31M  
Form chamfer to edges42M  
WALL INFILLS    
25MPa concrete0.20M3  
Formwork to sides of last 100–200 wide13M  
SUMP    
25MPa concrete0.1M3  
Formwork to last1.6M2  
Form opening for 100 dia pipe2No  
Form recess in edge of walls to support cover1.4M  
Supply and cast in 560 long × 100 dia galvanised steel pipe complete with bends1No  
FLOOR RINGS    
Supply and cast into floor slab floor rings all as detailed2No  
DOOR STOPS    
Take delivery of 50 × 50 × 5 L × 200 long and cast into concrete apron4No  
TOTAL CARRIED TO SUMMARY 

REINFORCING STEEL

Reinforcing weights have been calculated from standard average tables and no allowanc has been made for rolling margin.

Rates shall include for the supply, cutting, bending, cranking, hooking, delivery and placing, and for all necessary tie wire, chairs, spacers and the like.

 QUANTITYUNIT UNIT RATETOTAL PRICE
FOUNDATION AND SLAB    
D12 rods to foundations49kg  
D16 rods as column starters38kg  
R10 rods as slab starters22kg  
COLUMNS    
D16 rods to columns211kg  
D12 rods as lintel starters11kg  
R6 ties20kg  
LINTELS    
D12 rods31kg  
R6 ties7kg  
DOOR PILLARS    
D12 rod5kg  
WALL INFILLS    
D12 rods9kg  
SUMP    
D12 rods16kg  
D12 rod 200mm long welded to steel pipe1No  
TOTAL CARRIED TO SUMMARY 

CONCRETE MASONRY/BRICKWORK

Rates for both concrete masonry and brickwork shall include for all straight cutting, cutting of holes and chases for pipes, clean out of openings, cleaning down on completion and for making good on completion.

Rates shall also include for pointing of exposed joints.

 QUANTITYUNIT UNIT RATE TOTAL PRICE
EITHER:    
150mm hollow concrete blocks laid in stretcher bond26M2  
OR:    
100mm solid fired clay bricks laid in stretcher bond26M2  
TOTAL CARRIED TO SUMMARY 

METAL WORK

Rates shall include for the supply, fabrication, delivery, hoisting and erecting complete in place cutting to length machining ends and for any temporary bracing and templates.

Rates for welding shall include for all necessary preparation of metals and for grinding off all exposed welds.

Rates for bolts shall include for nuts and washers.

Rates for plates, cleats and the like shall include for all cutting.

All weights have been calculated from standard tables and no allowance has been made for rolling margin.

 QUANTITYUNIT UNIT RATE TOTAL PRICE
CASTING INTO CONCRETE    
Supply and hand to Concretor 50 × 50 × 5 L, 400mm long, drilled twice to take M12 bolts8No  
Ditto 50 × 6 × 180 long ms flat, drilled once to take M20 rod6No  
Ditto 200 long, 50 × 50 × 5 L with rubber buffer4No  
CHANNEL GRATING    
FW3 web grating 1200mm long × 250 wide1No  
CHANNEL OUTLET GRATE    
150 dia galvanised metal grating over channel outlet1No  
SUMP    
410 × 320 × 6mm plate as sump cover1No  
CARCASS RAILS    
M20 rod with threaded ends, and double nuts to each end17kg  
50 × 50 × 5 L drilled three times for M12 bolts and once for M20 rod90kg  
Ex 60 × 5 steel flat 110mm long11No  
75 × 12 steel flat56kg  
Extra value for forming to bend1SUM  
4mm site fillet weld3.5M  
Allow to coat meat rails with an edible oil1SUM  
PRIMING    
Prepare and apply one coat of anit-corrosive primer to all steel work9M2  
PIG SCALD TANK    
Construct the pig scalding tank, Equipment No. 2.1 all as detailed on drawing 13, complete with lifting cradle1No  
SCRAPING TABLE    
Construct the scraping table, Equipment No. 2.3 all as detailed on drawing 141No  
VISCERA INSPECTION TABLE    
Construct the viscera inspection table, Equipment No. 3.2 all as detailed on drawing 141No  
DRESSING CRADLE    
Construct the dressing cradle, Equipment No. 4.1 all as detailed on drawing 151No  
GUT BUGGY    
Construct standard designed gut buggy Equipment No. 4.7 from galvanised mild steel (or optionally stainless steel) with stainless steel pluck pan (Koch 1701.11 or similar)1No  
TOTAL CARRIED TO SUMMARY 

CARPENTRY

Rates shall include for all labours, cutting, notching, mitres, housing, scribes, sinkings, machining, fixings other than bolts, metal anchors and connectors, and for all waste and laps.

Rates for all types of bolts shall include for boring of timber and for all nuts and washers.

Rates for cladding shall include for stopping all nail holes, joints and imperfections.

 QUANTITYUNIT UNIT RATE TOTAL PRICE
WALLS    
100 × 50 timber framing168M  
Bituminous as damp proof course to last54M  
150 × 50 building mesh fixed to timber framing19M2  
Nylon insect mesh tied to last19M2  
Glavanised beading strip42M  
7.5mm thick asbestos cement or similar fibre cement cladding17M2  
Prepare prime and apply two coats high gloss enamel to asbestos cement wall cladding.33M2  
MISCELLANEOUS    
0.4mm galvanised iron shield screw fixed to wall, girth 225mm6M  
Prepare, prime and apply 2 coats high gloss enamel to last1.4M2  
Hardwood rubbing block bolted to wall6.2M  
M12 bolts12No  
TOTAL CARRIED TO SUMMARY 

END ROOF FRAMES

Refer to the preambles in the “Carpentry Trade Section”.

 QUANTITYUNIT UNIT RATE TOTAL PRICE
100 × 50 rafters12M  
R6 wire tie and staple4No  
100 × 50 purlins68M  
100 × 50 blocking between rafters14M  
Ditto between purlins12M  
150 × 50 blocking member to rafters, each 200 long4No  
M12 bolts last4No  
Bituminous damp proof course between concrete and timber blocking4No  
100 × 50 nailing block to take lifting beam each 370mm long8No  
100 × 50 nailing block to take purlins each 200mm long20No  
100 × 50 fascia board12M  
TOTAL CARRIED TO SUMMARY 

ROOF STRUCTURE
OPTION A - TIMBER

Refer to the preambles in the “Carpentry Trade Section”.

 QUANTITYUNIT UNIT RATE TOTAL PRICE
250 × 32 bottom chord nailed together17M  
R6 wire tie and staple4No  
Form 80 × 30 bevel on top edge of bottom chord4No  
M12 bolts8No  
Bitumious damp-proof course4No  
100 × 50 rafters12M  
100 × 50 truss member3.3M  
5/75 Nails6No  
100 × 50 bracing2.9M  
150 × 50 brace2M  
6 × 60 LNG nail plates2No  
M12 bolts9No  
65 × 65 washers4No  
R6 wire ties from R20 rod to purlin above4No  
60 × 5 flat, 220mm long drilled 2 times for M12 bolts and once for R20 rod4No  
R20 rod35kg  
150 × 50 blocking member to truss, each 200 long4No  
M12 bolts to last4No  
Bituminous damp-proof course between concrete and timber blockings4No  
100 × 50 nailing block to take purlins each 200mm long20No  
200 × 25 ridgeboard2.1M  
TOTAL CARRIED TO SUMMARY 

ROOF STRUCTURE
OPTION B - WELDED STEELWORK

Refer to the preambles in the “Metalwork Trade Section”.

 QUANTITYUNIT UNIT RATE TOTAL PRICE
50 × 50 × 5 L as bottom chord49kg  
Splay cut ends6No  
50 × 50 × 5 L as rafter47kg  
Splay cut ends4No  
50 × 50 × 5 L as struts29kg  
Double splay cut ends8No  
Splay cut ends8No  
136 × 90 × 6mm plate cut to shape, drilled twice for M12 bolts4No  
M12 bolts, 40mm long8No  
100 × 80 × 5 purlin cleat drilled twice for M12 bolts20No  
M12 bolts 125mm long40No  
50 × 50 × 5 L as truss bracing17kg  
Double splay cut ends2No  
50 × 50 × 5 cleat drilled once for M12 bolts3No  
M12 bolts3No  
R20 rod35kg  
100 × 40 × 6mm plate cut to shape4No  
4mm fillet welds4.3M  
4mm single v butt weld10.4M  
4mm double fillet weld4.4M  
Prepare and apply one coat of zinc anti-corrosive primer to all steelwork7.7M2  
Apply 2 coats of enamel to exposed steelwork7.7M2  
TOTAL CARRIED TO SUMMARY  

ROOF STRUCTURE
OPTION C - BOLTED STEELWORK

Refer to the preambles in the “Metalwork Trade Section”.

 QUANTITYUNITUNIT RATE TOTAL PRICE
50 × 50 × 5 L as bottom chord49kg  
Splay cut ends6No  
50 × 50 × 5 L as rafter47kg  
50 × 50 × 5 L as struts29kg  
Drill all of last for M12 bolts88No  
M12 bolts56No  
Ex 200 × 130 × 6mm plate cut to shape and drilled four times for M12 bolts4No  
100 × 80 × 5mm purlin cleat drilled twice for M12 bolts20No  
94 × 54 × 5mm angle plate drilled4No  
4 times for M12 bolts    
M12 bolts16No  
Drill 50 × 50 × 5 L for last24No  
40 × 40 × 5mm plate spacers once drilled for M12 bolts9No  
M12 bolts9No  
Drill 50 × 50 × 5 L for last9No  
50 × 50 × 5 L as truss bracing17kg  
50 × 50 × 5 cleat once drilled for M12 bolts3No  
Drill 50 × 50 × 5 L for last3No  
M12 bolts3No  
R20 rod35kg  
100 × 40 × 6mm plate cut to shape and drilled once for M12 bolt4No  
M12 bolts4No  
5mm fillet weld0.4M  
4mm double fillet weld4M  
Prepare and apply one coat of zinc anti-corrosive primer to all steelwork7.9M2  
Apply 2 coats of enamel to exposed steelwork7.9M2  
TOTAL CARRIED TO SUMMARY  

LIFTING BEAM
OPTION A - TIMBER

Refer to the preambles in the “Carpentry Trade Section”.

 QUANTITYUNITUNIT RATETOTAL PRICE
200 × 50 lifting beam, nailed16M  
together    
200 × 50 beam1.5M  
M12 bolts with 50 × 50 × 3 washers33No  
M12 bolts6No  
50 × 50 × 5 angle 450 long drilled2No  
6 times for M12 bolts    
TOTAL CARRIED TO SUMMARY 

LIFTING BEAM
OPTION B - STEEL

Refer to the preambles in the “Metalwork Trade Section”.

 QUANTITYUNIT UNIT RATE TOTAL PRICE
102 × 51 channel lifting beam83kg  
102 × 51 channel beam16kg  
100 × 50 spacer block1No  
Drill channel for 12mm bolts for last2No  
M12 bolts 200mm long2No  
50 × 50 × 5 angle 100mm long1No  
Drill last for M12 bolts4No  
M12 bolts 35mm long4No  
Prepare and apply one coat of zinc anti-corrosive primer to steelwork3.9M2  
Apply 2 coats of enamel to exposed3.9M2  
steelwork    
TOTAL CARRIED TO SUMMARY 

DOORS
OPTION A - (Timber Frame)

Refer to the preambles in the “Carpentry” and “Metalwork” Trade Sections.

 QUANTITYUNITUNIT RATETOTAL PRICE
75 × 12 rail88kg  
60 × 60 × 12mm thick steel packers58No  
100mm dia. steel wheel8No  
3mm washer behind last8No  
M16 axle bolt approx. 120mm long8No  
60 × 5 × 160mm long ms straps16No  
M12 bolts 80mm long16No  
Adjustable door stops to ends of rail8No  
25 NB tube 200mm long set into concrete apron4No  
75 × 50 packers fixed to concrete20M  
Bituminous damp-proof course between concrete and last20M  
100 × 50 door frame52M  
EITHER:    
9mm plywood cladding15M2  
OR:    
12mm dressed timber15M2  
Prime cladding and frame with an oil based alkyd and apply 2 coats high gloss exterior paint45M2  
Prepare and apply one coat of zinc anti-corrosive primer and 2 coats of enamel to all steelwork3.1M2  
HARDWARE    
Galvanised D type handle fixed to cladding4No  
Ditto fixed to timber frame4No  
Hasp and staple4No  
TOTAL CARRIED TO SUMMARY 

DOORS
OPTION B – (Steel Frame)

Refer to the preambles in the “Metalwork Trade Section”.

 QUANTITYUNIT UNIT RATETOTALPRICE
75 × 12 rail88kg  
60 × 60 × 12mm thick steel packers58No  
100mm dia. steel wheel8No  
3mm washers behind last8No  
R16 axle pin welded to angle8No  
60 × 60 × 5 ms plate8No  
100 × 100 × 5 ms plate8No  
Adjustable door stops to ends of rail8No  
25 NB tube 200mm long set into concrete apron4No  
75 × 50 packers fixed to concrete20M  
Bituminous damp-proof course between20M  
concrete and last    
50 × 50 × 5 L as frame201kg  
Double splay cut ends16No  
Welding10M  
1.3mm thick galvanised flat sheet cladding screw fixed to steel frame16M2  
Prepare and apply one coat of zinc anti-corrosive primer and 2 coats of enamel to steelwork10M2  
HARDWARE    
Galvanised D type handle fixed to cladding4No  
Ditto fixed to steel frame4No  
Hasp and staple4No  
TOTAL CARRIED TO SUMMARY 

ROOF CLADDING

Rates for roofing shall include for all straight cutting, fixings, laps and priming where applicable.

Rates for flashings and the like shall include for all joints in running length, expansion joints and for all fixings.

 QUANTITYUNITUNIT RATETOTAL PRICE
0.4mm corrugated galvanised roofing iron fixed to timber purlins42M2  
Galvanised iron lead edge ridge capping6.8M  
Galvanised iron verge flashings12M  
TOTAL CARRIED TO SUMMARY  

PLUMBING

All work shall comply with the construction requirements as laid down by Government or Local Authority.

Rates for pipework shall include for all running joints, supports, fixings and for boring or checking of timber as required.

Rates for pipework of less than 25 dia shall include for all fittings such as, bends, elbows, junctions and the like.

Rates for valves and the like shall include for all joints to pipework.

Pipework to the amenities block has not been included.

 QUANTITYUNITUNIT RATETOTAL PRICE
COLD WATER SUPPLY    
25mm dia medium galvanised pipework laid in trench (provisional measure)43M  
Ditto in free standing vertical rise4M  
Ditto in vertical rise fixed to concrete block wall6M  
Ditto in horizontal run fixed to timber work6.5M  
Extra value over pipework for bends13No  
Ditto for 25 × 25 × 25 tee junction5No  
Allow for connection to existing 25mm dia. pipework1SUM  
Ditto to boiler1No  
HOT WATER SUPPLY    
25mm dia. medium galvanised pipework laid in trench9M  
Ditto in vertical rise fixed to concrete blockwork10M  
Ditto in horizontal run fixed to timber work10M  
Extra value over pipework for bends7No  
Ditto for 25 × 25 × 25 tee junction1No  
Allow for connection to boiler1No  
STEAM PIPEWORK    
25mm dia black medium pipework as overhead pipework, rising from the boiler. Include for all vertical supports as required9M  
Ditto in horizontal run fixed to concrete blockwork7M  
Extra value over pipework for bends5No  
Allow for connection to boiler1No  
VALVES    
Supply and fit 25mm dia. isolating valve to water supply pipework3No  
Ditto foot operated water valves to ditto (Koch 1929 or similar)4No  
Ditto to steam pipework2No  
FITTINGS    
Supply and fix suitable wash hand basin to concrete block walls. Basins to be complete with galvanised iron frame and back splash2No  
Supply and install water tank all as detailed on drawing1No  
Ditto water pump all as specified1No  
GENERAL    
Allow to pressure test the pipework on completion SUM  
TOTAL CARRIED TO SUMMARY 

SOLID PLASTER

Rates shall include for preparation of all surfaces to receive plaster.

Rates shall include for making good around and pointing up to pipes, brackets and the like and for all internal angles.

 QUANTITYUNITUNIT RATETOTAL PRICE
20mm solid plaster in 3 coats to concrete and concrete block (or brick) walls34M2  
Ditto to channel 330 girth5.6M  
Extra value over last for coving24M  
Ditto for external curved angle5.6M  
Form coving at wall and floor junction7.2M  
TOTAL CARRIED TO SUMMARY 

ELECTRICAL

 QUANTITYUNITUNIT RATETOTAL PRICE
Supply, install and connect up suitable mains cable, run from the supply authorities main to connect to the switchboard located on exterior wall1No  
Provide suitable meter to the supply authorities requirements1No  
Supply, install and wire up complete suitable switchboard. Include for metal cabinet and fixing to exterior wall1No  
Wire up for light switches, run from switchboard2No  
Wire up for light outlets5No  
Supply and install, 2 tube × 65 watt batten type fluorescent light fittings. Include for tubes4No  
Ditto 70 watt self ballasted mercury vapour light fitting. Include for weatherproof housing and lamp1No  
Wire and connect up water pump1No  
Ditto hoist1No  
TOTAL CARRIED TO SUMMARY 

MODULAR SMALL ABATTOIR
AND MEAT MARKET
LAIRAGE
SUMMARY

  $
Excavation  
Concrete  
Reinforcing Steel  
Concrete Masonry/Brickwork  
Metal Work  
Carpentry  
Gates  
Roof Cladding  
Plumbing  
Electrical  
TOTAL CARRIED TO MAIN SUMMARY 

EXCAVATION

 QUANTITYUNITUNIT RATETOTAL PRICE
Clear site of all vegetation88M2  
Excavate down to sand level2.4M3  
Excavate for footings3.4M3  
Extra value for forming batter31.4M  
Backfill to foundations1.3M3  
Remove surplus spoil2.1M3  
50mm blinding sand under slab48M2  
SUMP    
Excavate for sump0.22M3  
Backfill0.11M3  
Remove surplus spoil0.11M3  
  TOTAL CARRIED TO SUMMARY  

CONCRETE

 QUANTITYUNITUNIT RATETOTAL PRICE
FOUNDATIONS AND SLAB    
25 MPa concrete8.1M3  
Formwork 0–200mm wide to form channel31.4M  
Form slab to falls48M3  
Provide broom finish to slab48M2  
0.25mm thick polythene damp-proof48M2  
sheet    
Form construction joint to floor13M  
slab. Include for 20 × 10    
polysulphide sealant    
COLUMNS    
EITHER OPTION A    
25 MPa concrete1.4M3  
Formwork to sides of last 200mm wide13.3M  
Take delivery and cast in 440 × 60 × 64 rafter fixing plate to to of columns16No  
OR OPTION B    
25 MPa concrete0.9M3  
Formwork to sides of last 200mm wide87M  
LINTELS    
25 MPa concrete0.4M3  
Formwork to sides of last 200mm wide30M  
SUMP    
25 MPa concrete0.1M3  
Formwork to last1.6M2  
Form opening for 100 dia. pipe2No  
Form recess in edge of walls to support cover1.4M  
Supply and cast in 560 long × 100 dia. pipe complete with bends1No  
TOTAL CARRIED TO SUMMARY  

REINFORCING STEEL

 QUANTITYUNITUNIT RATETOTAL PRICE
FOUNDATION AND SLAB    
D12 rods to foundations63kg  
D12 rods as column starters25kg  
R10 rods as slab starters28kg  
COLUMNS    
EITHER OPTION A    
D12 rods104kg  
R6 ties19kg  
OR OPTION B (No Roof)    
D12 rod43kg  
R6 ties6kg  
LINTELS    
D12 rod34kg  
R6 ties4kg  
SUMP    
D12 rods9kg  
TOTAL CARRIED TO SUMMARY  

CONCRETE MASONRY/BRICKWORK

 QUANTITYUNITUNIT RATETOTAL PRICE
EITHER    
150mm hollow concrete blocks laid in stretcher bond40M2  
OR    
100mm solid fired clay bricks laid in stretcher bond40M2  
TOTAL CARRIED TO SUMMARY  

METAL WORK

 QUANTITYUNITUNIT RATETOTAL PRICE
OPTION A    
ROOF BRACING    
20mm dia. rod brace threaded each end (in 4 No. lengths)26M  
FIXING PLATES    
440 × 60 × 6 rafter fixing plate drilled twice for M16 bolt with end splayed16No  
OR OPTION B    
No roof    
TOTAL CARRIED TO SUMMARY  

CARPENTRY

 QUANTITYUNITUNIT RATETOTAL PRICE
OPTION A    
ROOF FRAMING    
300 × 50 rafters49M  
300 × 50 fascia board21M  
200 × 50 purlin52M  
150 × 50 purlin9M  
100 × 50 brace5M  
M16 × 150mm long bolt16No  
3 ply malthoid damp proof course in 200 × 100mm squares8No  
OR OPTION B    
No Roof    
TOTAL CARRIED TO SUMMARY  

GATES

Gates are as per details on Drawing 9.

All welds to metal gates shall be 5mm fillet welds.

 QUANTITYUNITUNIT RATETOTAL PRICE
EITHER OPTION A    
METAL FRAMED GATES    
Gate type G1 size 1400 high × 1155 wide1No  
Gate type G2 size 1100 high × 1250 wide1No  
Gate type G3 size 1400 high × 1650 wide4No  
Gate type G4 size 1100 high × 1650 wide4No  
Gate type G5 size 1400 high × 1450 wide1No  
OR OPTION B    
TIMBER FRAMED GATES    
Gate type G1 size 1400 high × 1155 wide1No  
Gate type G2 size 1100 high × 1250 wide1No  
Gate type G3 size 1400 high × 1650 wide4No  
Gate type G4 size 1100 high × 1650 wide4No  
Gate type G5 size 1400 high × 1450 wide1No  
TOTAL CARRIED TO SUMMARY  

ROOF CLADDING

 QUANTITYUNITUNIT RATETOTAL PRICE
0.4mm corrugated galvanised roofing iron fixed to timber purlins68M2  
Galvanised iron flashings21M  
TOTAL CARRIED TO SUMMARY  

PLUMBING

 QUANTITYUNITUNIT RATETOTAL PRICE
COLD WATER SUPPLY    
25mm dia. medium galvanised pipework laid in trench (provisional measure)3M  
Ditto in vertical rise fixed to concrete block wall1M  
Extra value over pipework for bends2No  
Ditto for 25 × 25 × 25 tee junction1No  
VALVES    
Supply and fit 25mm dia. belating valve to water supply pipework1No  
TOTAL CARRIED TO SUMMARY  

ELECTRICAL

 QUANTITYUNITUNIT RATETOTAL PRICE
Wire up for light switch, run from switchboard in slaughter house. Switch to be located on interior end wall of the slaughter house1No  
Wire up for light outlets3No  
Supply and install 100 watt GLS lamp and BC holders3No  
TOTAL CARRIED TO SUMMARY  

MODULAR SMALL ABATTOIR
AND MEAT MARKET
TRIPERY BUILDING

  $
Excavation  
Concrete  
Reinforcing Steel  
Masonry  
Metalwork  
Carpentry  
Doors  
Option A - Timber Frame  
Option B - Steel Frame  
Roof Cladding  
Plumbing  
Drainage  
Solid Plaster  
Electrical  
TOTAL CARRIED TO MAIN SUMMARY  

Refer to the Slaughter House Schedule for the preliminaries and trade preambles.

EXCAVATION

 QUANTITYUNITUNIT RATETOTAL PRICE
Clear site of all vegetation16M2  
Excavate down to slab level0.6M3  
Excavate for footings0.8M3  
Extra value for forming batter10M  
Backfill to foundations0.4M3  
Remove surplus spoil from site1M3  
PAUNCH SLAB    
Excavate for paunch slab1.2M3  
Backfill0.2M3  
Remove surplus spoil1M3  
SUMP    
Excavate for sump0.22M3  
Backfill0.11M3  
Remove surplus spoil0.11M3  
 TOTAL CARRIED TO SUMMARY   

CONCRETE

 QUANTITYUNITUNIT RATETOTAL PRICE
FOUNDATIONS AND SLAB    
25 MPa concrete1.4M3  
Formwork to last3.1M2  
Form 100 × 20 deep recess in slab11.6M  
Form 70 × 20 rebate3.3M  
Form slab to falls9.2M2  
Provide broom finish to slab9.2M2  
0.25mm thick polythene damp-proof sheet7.8M2  
COLUMNS    
25 MPa concrete0.23M3  
Formwork to sides of last 150mm wide42M  
LINTELS    
25 MPa concrete0.4M3  
Formwork to sides 150mm wide27M  
Soffit formwork 150mm wide17M  
Supply and cast in 6 dia. wire ties (approx. length each 650mm)10No  
Supply and cast in M10 bolts 125mm long12No  
Ditto M12 bolts 140mm long5No  
DOOR PILLARS    
25 MPa concrete0.04M3  
Formwork 200 – 300 wide4.5M  
Formwork 100 – 200 wide4.5M  
Form chamfer to edges7M  
Take delivery of 200mm long 50 × 10 × 5 L and cast into concrete apron1No  
PAUNCH SLAB    
25 MPa concrete0.87M3  
Formwork 300mm wide4.2M  
Formwork 250 mm wide1.9M  
Formwork 150mm wide5.9M  
Formwork 100mm wide1.2M  
Form slab to falls7M2  
Form 240 × 80 deep channel3.3M  
Form 20 × 20 deep rebate4M  
Form 70 × 20 recess in wall of upstand4M  
Supply and cast in 560 long 100 dia. galvanised steel pipe complete with bends1No  
SUMP    
25 MPa concrete0.1M3  
Formwork to last1.6M2  
Form opening for 100 dia. pipe2No  
Form recess in edge of walls to support cover1.4M  
 TOTAL CARRIED TO SUMMARY   

REINFORCING

 QUANTITYUNITUNIT RATETOTAL PRICE
FOUNDATIONS AND SLAB    
D12 rods to foundations17kg  
D12 rods as column starters3kg  
R10 rods as slab starters14kg  
COLUMNS    
D12 rods9kg  
LINTELS    
D12 rods26kg  
R6 ties2kg  
DOOR PILLARS    
D12 rod2kg  
PAUNCH SLAB    
D12 rods as dowels to foundations of building3kg  
D12 rods9kg  
SUMP    
D12 rods16kg  
D12 200 long welded to steel pipe1No  
 TOTAL CARRIED TO SUMMARY   

MASONRY

 QUANTITYUNITUNIT RATETOTAL PRICE
EITHER:    
150mm hollow concrete blocks laid in stretcher bond21M2  
Rake cutting of blocks5M  
OR:    
100mm solid fired clay bricks laid in stretcher bond21M2  
Rake cutting of bricks5M  
 TOTAL CARRIED TO SUMMARY   

METAL WORK
 QUANTITYUNITUNIT RATETOTAL PRICE
CASTING INTO CONCRETE    
Supply and hand to Concretor 200 long, 50 × 50 × 5 galvanised L1No  
RAIL    
100 × 50 × 3.2 RHS (total weight 23kg)3.2M  
Site cut last to suit1No  
150 × 150 × 6mm plate welded to RHS with 3/14 dia. drilled holes (total weight 1.1kg)1No  
Ditto site welded to RHS, ditto (total weight 1.1kg)1No  
200mm long ×50 × 12 ms flat welded to RHS and cut to shape (in 4 No)4kg  
75 × 12 ms flat welded to last22kg  
M12 Masonry anchors6No  
4mm fillet weld0.8M  
4mm site fillet weld0.3M  
Prepare and apply one coat of zinc anti-corrosive primer and 2 coats of enamel to all steelwork1.7M2  
PAUNCH SUMP COVERS    
420 × 320 × 6mm plate as sump cover1No  
WASH TROUGH    
Construct wash trough Equipment No. 8.2 all as detailed on drawing 141No  
CHANNEL GRATE    
150 dia. cast iron grate over sump outlet1No  
TOTAL CARRIED TO SUMMARY  