M. Steps to be taken in developing a NPOA-IUU


REPORT OF WORKING GROUP 1

1) Which Ministries/Departments are involved in the elaboration of an NPOA-IUU?

2) What constraints are likely to be faced in the elaboration of an NPOA-IUU?

3) How can these constraints be overcome?

4) How national resources could be mobilized for the elaboration of an NPOA-IUU?

5) What considerations could affect the ability of countries to deliver an NPOA-IUU?

6) Steps to be undertaken in elaborating an NPOA-IUU

ACTIVITY

APPROVALS REQUIRED

STARTING DATE

FINISHING DATE

1. Policy review/development

Minister/Cabinet

1/1/2005

10/2005

2. Legislation review/development

Minister/Cabinet

2/2005

10/2005

3. Develop the NPOA

Minister/Cabinet

1/2005

12/2005

4. Implementation of NPOA

Fisheries Department/MCS Agencies and Minister

1/2006

ongoing

***

REPORT OF WORKING GROUP 2

1) Which Ministries/Departments are involved in the elaboration of an NPOA-IUU?

2) What constraints are likely to be faced in the elaboration of an NPOA-IUU

3) How can these constraints be overcome?

4) How national resources could be mobilized for the elaboration of a NPOA-IUU?

5) What considerations could affect the ability of countries to deliver a NPOA-IUU

6) Steps to be undertaken in elaborating a NPOA-IUU

ACTIVITY

APPROVALS REQUIRED

STARTING DATE

FINISHING DATE

1. Consultation with stakeholders


1/1/2005*


2. Policy review/development

Cabinet/National consultation/Minister



3. Legislation review/development

Parliament or equivalent/Chief Parliamentary Council



4. Develop NPOA

Ministry of Fisheries or equivalent



5. Implement NPOA

Relevant Government bodies



* Only date that can be confirmed.

***

REPORT OF WORKING GROUP 3

1) Which Ministries/Departments are involved in the elaboration of an NPOA-IUU?

2) What constraints are likely to be faced in the elaboration of an NPOA-IUU?

3) How can these constraints be overcome?

4) How national resources could be mobilized for the elaboration of a NPOA-IUU?

5) What considerations could affect the ability of countries to deliver a NPOA-IUU?

6) Steps to be undertaken in elaborating a NPOA-IUU

ACTIVITY

APPROVALS REQUIRED

STARTING DATE

FINISHING DATE

1. Policy review/development

Fisheries Minister

1/1/2005

31/3/2005

2. Legislation review/development

Assembly

1/4/2005

31/3/2006

3. Develop the NPOA

Cabinet

1/4/2006

30/9/2006

4. Implementation of NPOA

Chief Fisheries Officer

1/10/2006

1/10/2007
1st review

***

REPORT OF WORKING GROUP 4

1) Which Ministries/Departments are involved in the elaboration of an NPOA-IUU?

2) What constraints are likely to be faced in the elaboration of an NPOA-IUU?

3) How can these constraints be overcome?

4) How national resources could be mobilized for the elaboration of a NPOA-IUU?

5) What considerations could affect the ability of countries to deliver a NPOA-IUU

6) Steps to be undertaken in elaborating a NPOA-IUU

ACTIVITY

APPROVALS REQUIRED

STARTING DATE

FINISHING DATE

1. Policy review/development

Yes

1/2005

7/2005

2. Legislation review/development

Yes

7/2005

12/2005

3. Develop the NPOA

Yes

1/2006

12/2006

4 Legislation development

Yes

8/2006

8/2007

5. Implementation of NPOA


8/2007

8/2009