Construction costs were calculated for ponds of one hectare each and for the monoculture of P. monodon and L. calcarifer. These costs and the economic data following, form a basis for a first level approximation. In succeeding steps, beyond the scope of the project, the size and configuration of ideal fish farms should allow to develop a final model for use in siting studies.
The kind of pond used for costing is illustrated by Fig. 1.3, in which the only excavations are for the sheltering canal or most around the outer periphery of the pond and for the various canals. Other cost factors were developed on a preliminary basis. Unit costs in $ (M)1 are generally from current engineering estimating costs used by the Fisheries Division (English units):
P. monodon idealized 1-ha pond cost
Sheltering canal:
Volume | = | ![]() | ||
= | 3 139 y3 | |||
Cost | = | 3 139 × $1.80 | $ 5 650 | |
Clearing: | ||||
Cost | = | (2.4 acres) × ($600) 1.3 | 1 872 | |
(1.3 is a factor which allows for other clearing costs) | ||||
Canals (judgmental) | 5 600 | |||
Pumps and installation (3 000 GPM, 10 HP) | $ 15 000 | |||
Gates and control structures (by comparisons) | 12 000 | |||
Roads and infrastructure | 7 500 | |||
Total construction cost | $ 47 622 | |||
say | $ 48 000/ha |
The pond used for the 1 ha costing is based on the cross section for the baik Pulau site, as shown in Fig. 1.2.
Pond excavation:
Volume | = | ![]() | |
Cost | = | 23 932 × $1.80 | $43 061 |
Clearing:
Cost = 2.4 × $600 × 1.3 | 1 872 | |
Canals, dikes, etc. 20% × 43 061 | 8 600 | |
Pumps and installation (3 000 GPM × 10 HP) | 15 000 | |
Gates and control structures | 18 000 | |
Roads and infrastructure | 10 000 | |
Total construction cost | $96 533 | |
say | $ 97 000/ha |