PROJECT TITLE: | Evaluation Tank Enforcement Act | CODE: F-04 |
STATION OF EXECUTION: | FARS, Mymensingh | |
PROGRAMME: | Socio-economic studies | |
RESEARCH AREA (S): | CODE(S): | |
- Socio-economics | 14–03/14–08 |
OBJECTIVIES:
TIME SCHEDULE: | ||||
- DATE OF COMMENCEMENT: | 01.01.1988 | |||
- DATE OF COMPLETION: | 31.12.1988 | |||
MANPOWER: | YEAR 1 | YEAR 2 | YEAR 3 | |
- NO OF RESEARCHERS: | 1 | - | - | |
- NO OF SUPPORTING STAFF: | - | - | - | |
ESTIMATED BUDGET (in Taka): | ||||
- OPERATIONAL EXPENSES: | 100,000 | |||
- CAPITAL EXPENSES: | - | |||
- TOTAL: | 100,000 |
PROJECT TITLE: | Pen and cage culture of mono- and mixed cultures | CODE: G-01 |
STATION OF EXECUTION: | FARS, Mymensingh | |
PROGRAMME: | Pen and cage culture | |
RESEARCH AREA(S): | CODE(S): | |
- Cage/pen production management | 03-02/03-03 | |
- Socio-economics | 14–05 |
OBJECTIVES:
TIME SCHEDULE: | ||||
- DATE OF COMMENCEMENT: | 01.05.1987 | |||
- DATE OF COMPLETION: | 30.04.1989 | |||
MANPOWER: | YEAR 1 | YEAR 2 | YEAR 3 | |
- NO OF RESEARCHERS: | 1 | 1 | - | |
- NO OF SUPPORTING STAFF: | 1 | 1 | - | |
ESTIMATED BUDGET (in Taka): | ||||
- OPERATIONAL EXPENSES: | 310,000 | |||
- CAPITAL EXPENSES: | 170,000 | |||
- TOTAL: | 480,000 |
PROJECT TITLE: | Stock assessment and population dynamics of Hilsa | CODE: H-01 |
STATION OF EXECUTION: RFRS, Chandpur | ||
PROGRAMME: | Riverine production ecology | |
RESEARCH AREA(S): | CODE(S): | |
- Riverine fisheries production management | 06–01/06–03 | |
- Socio-economics | 14–08 |
OBJECTIVES:
TIME SCHEDULE: | ||||
- DATE OF COMMENCEMENT: | 01.04.1986 | |||
- DATE OF COMPLETION: | 31.03.1989 | |||
MANPOWER: | YEAR 1 | YEAR 2 | YEAR 3 | |
- NO OF RESEARCHERS: | 6 | 6 | 6 | |
- NO OF SUPPORTING STAFF: | 20 | 20 | 20 | |
ESTIMATED BUDGET (in Taka): | ||||
- OPERATIONAL EXPENSES: | 9,425,000 | |||
- CAPITAL EXPENSES: | 2,150,000 | |||
- TOTAL: | 11,575,000 |
PROJECT TITLE: | Stock assessment and population dynamics of major carp | CODE: H-01 |
STATION OF EXECUTION: | RFRS, Chandpur | |
PROGRAMME: | Riverine production ecology | |
RESEARCH AREA(S): | CODE(S): | |
- Riverine fisheries production management | 06–01/06–03 | |
- Socio-economics | 14–08 |
OBJECTIVES:
TIME SCHEDULE: | ||||
- DATE OF COMMENCEMENT: | 01.09.1986 | |||
- DATE OF COMPLETION: | 31.08.1989 | |||
MANPOWER: | YEAR 1 | YEAR 2 | YEAR 3 | |
- NO OF RESEARCHERS: | 2 | 2 | 2 | |
- NO OF SUPPORTING STAFF: | 10 | 10 | 10 | |
ESTIMATED BUDGET (in Taka): | ||||
- OPERATIONAL EXPENSES: | 2,000,000 | |||
- CAPITAL EXPENSES: | 1,000,000 | |||
- TOTAL: | 3,000,000 |
PROJECT TITLE: | Stock assessment and population population dynamics of Macrobrachium | CODE: H-02 |
STATION OF EXECUTION: RFRS, Chandpur | ||
PROGRAMME: | Riverine production ecology | |
RESEARCH AREA(S): | CODE(S): | |
- Riverine fisheries production management | 06–02/06–03 | |
- Socio-economics | 14–08 |
OBJECTIVES:
TIME SCHEDULE: | ||||
- DATE OF COMMENCEMENT: | 01.09.1986 | |||
- DATE OF COMPLETION: | 31.08.1989 | |||
MANPOWER: | YEAR 1 | YEAR 2 | YEAR 3 | |
- NO OF RESEARCHERS: | 4 | 4 | 4 | |
- NO OF SUPPORTING STAFF: | 12 | 12 | 12 | |
ESTIMATED BUDGET (in Taka): | ||||
- OPERATIONAL EXPENSES: | 3,000,000 | |||
- CAPITAL EXPENSES: | 2,100,000 | |||
- TOTAL: | 5,100,000 |
PROJECT TITLE: | Survey of reproduction areas of riverine fish and shrimps | CODE: H-03 |
STATION OF EXECUTION: | RFRS, Chandpur | |
PROGRAMME: | Riverine production ecology | |
RESEARCH AREA(S): | CODE(S): | |
- Riverine fisheries production management | 06–03 |
OBJECTIVES:
TIME SCHEDULE: | ||||
- DATE OF COMMENCEMENT: | 01.05.1987 | |||
- DATE OF COMPLETION: | 31.09.1987 | |||
MANPOWER: | YEAR 1 | YEAR 2 | YEAR 3 | |
- NO OF RESEARCHERS: | 1 | - | - | |
- NO OF SUPPORTING STAFF: | 1 | - | - | |
ESTIMATED BUDGET (in Taka): | ||||
- OPERATIONAL EXPENSES: | 85,000 | |||
- CAPITAL EXPENSES: | 15,000 | |||
- TOTAL: | 100,000 |
PROJECT TITLE: | Impact of environmental changes on riverine production | CODE: H-04 |
STATION OF EXECUTION: | RFRS, Chandpur | |
PROGRAMME: | Riverine production ecology | |
RESEARCH AREA(S): | CODE(S): | |
- Riverine fisheries production management | 06–04 |
OBJECTIVES:
TIME SCHEDULE: | ||||
- DATE OF COMMENCEMENT: | 01.01.1987 | |||
- DATE OF COMPLETION: | 31.12.1989 | |||
MANPOWER: | YEAR 1 | YEAR 2 | YEAR 3 | |
- NO OF RESEARCHERS: | 2 | 2 | 2 | |
- NO OF SUPPORTING STAFF: | 2 | 2 | 2 | |
ESTIMATED BUDGET (in Taka): | ||||
- OPERATIONAL EXPENSES: | 630,000 | |||
- CAPITAL EXPENSES: | 210,000 | |||
- TOTAL: | 840,000 |
PROJECT TITLE: | Adaptive gear development | CODE: H-05 |
STATION OF EXECUTION: | RFRS, Chandpur | |
PROGRAMME: | Riverine production ecology | |
RESEARCH AREA(S): | CODE(S): | |
- Riverine fisheries production management | 06–05 | |
- Large freshwater bodies production management | 05–03 |
OBJECTIVES:
TIME SCHEDULE: | ||||
- DATE OF COMMENCEMENT: | 01.03.1987 | |||
- DATE OF COMPLETION: | 31.07.1988 | |||
MANPOWER: | YEAR 1 | YEAR 2 | YEAR 3 | |
- NO OF RESEARCHERS: | 1 | 1 | - | |
- NO OF SUPPORTING STAFF: | 1 | 1 | - | |
ESTIMATED BUDGET (in Taka): | ||||
- OPERATIONAL EXPENSES: | 195,000 | |||
- CAPITAL EXPENSES: | 25,000 | |||
- TOTAL: | 220,000 |
PROJECT TITLE: | Reproduction and nursing of Hilsa | CODE: I-01 |
STATION OF EXECUTION: | RFRS, Chandpur | |
PROGRAMME: | Reproduction and culture of riverine species | |
RESEARCH AREA(S): | CODE(S): | |
- Reproduction freshwater species | 09–05 | |
- Pond production management | 04–03 |
OBJECTIVES:
TIME SCHEDULE: | ||||
- DATE OF COMMENCEMENT: | 01.01.1987 | |||
- DATE OF COMPLETION: | 31.12.1989 | |||
MANPOWER: | YEAR 1 | YEAR 2 | YEAR 3 | |
- NO OF RESEARCHERS: | 1 | 1 | 1 | |
- NO OF SUPPORTING STAFF: | 1 | 1 | 1 | |
ESTIMATED BUDGET (in Taka): | ||||
- OPERATIONAL EXPENSES: | 720,000 | |||
- CAPITAL EXPENSES: | 270,000 | |||
- TOTAL: | 990,000 |
PROJECT TITLE: | Artificial reproduction and culture of Macrobrachium | CODE: I-02 |
STATION OF EXECUTION: | RFRS, Chandpur | |
PROGRAMME: | Reproduction and culture of riverine species | |
RESEARCH AREA(S): | CODE(S): | |
- Reproduction marine and brackishwater species | 08–01/08–05 | |
- Brackishwater production management | 02–02 | |
- Pond production management | 04–01/04–06 | |
- Nutrition and feed | 10–04 | |
- Socio-economics | 14–01/14–05 |
OBJECTIVES:
TIME SCHEDULE: | ||||
- DATE OF COMMENCEMENT: | 01.07.1987 | |||
- DATE OF COMPLETION: | 30.06.1990 | |||
MANPOWER: | YEAR 1 | YEAR 2 | YEAR 3 | |
- NO OF RESEARCHERS: | 2 | 2 | 2 | |
- NO OF SUPPORTING STAFF: | 3 | 3 | 3 | |
ESTIMATED BUDGET (in Taka): | ||||
- OPERATIONAL EXPENSES: | 550,000 | |||
- CAPITAL EXPENSES: | 400,000 | |||
- TOTAL: | 950,000 |
PROJECT TITLE: | Optimum farm design for Macrobrachium | CODE: I-03 |
STATION OF EXECUTION: | RFRS, Chandpur | |
PROGRAMME: | Reproduction and culture of riverine species | |
RESEARCH AREA(S): | CODE(S): | |
- Brackishwater production management | 02–02 | |
- Reproduction marine and brackishwater species | 08–05 |
OBJECTIVES:
TIME SCHEDULE: | ||||
- DATE OF COMMENCEMENT: | 01.07.1988 | |||
- DATE OF COMPLETION: | 30.06.1990 | |||
MANPOWER: | YEAR 1 | YEAR 2 | YEAR 3 | |
- NO OF RESEARCHERS: | 2 | 2 | - | |
- NO OF SUPPORTING STAFF: | 2 | 2 | - | |
ESTIMATED BUDGET (in Taka): | ||||
- OPERATIONAL EXPENSES: | 250,000 | |||
- CAPITAL EXPENSES: | 250,000 | |||
- TOTAL: | 500,000 |
PROJECT TITLE: | Aquaculture of other riverine species (Pangasius) | CODE: I-04 |
STATION OF EXECUTION: | RFRS, Chandpur | |
PROGRAMME: | Reproduction and culture of riverine species | |
RESEARCH AREA (S): | CODE(S): | |
- Reproduction freshwater species | 09–03 | |
- Pond production management | 04–05 | |
- Socio-economics | 14–05 |
OBJECTIVES:
TIME SCHEDULE: | ||||
- DATE OF COMMENCEMENT: | 01.03.1987 | |||
- DATE OF COMPLETION: | 28.02.1990 | |||
MANPOWER: | YEAR 1 | YEAR 2 | YEAR 3 | |
- NO OF RESEARCHERS: | 1 | 1 | 1 | |
- NO OF SUPPORTING STAFF: | 2 | 2 | 2 | |
ESTIMATED BUDGET (in Taka): | ||||
- OPERATIONAL EXPENSES: | 450,000 | |||
- CAPITAL EXPENSES: | 310,000 | |||
- TOTAL: | 760,000 |
PROJECT TITLE: | Hatchery production | CODE: I-05 |
STATION OF EXECUTION: | RFRS, Chandpur | |
PROGRAMME: | Reproduction and culture of riverine species | |
RESEARCH AREA(S): | CODE(S): | |
- Reproduction freshwater species | 09–01/09–07 | |
- Pond production management | 04–01/04–02 | |
- Socio-economics | 14–01 |
OBJECTIVES:
TIME SCHEDULE: | ||||
- DATE OF COMMENCEMENT: | 01.01.1987 | |||
- DATE OF COMPLETION: | 31.12.1989 | |||
MANPOWER: | YEAR 1 | YEAR 2 | YEAR 3 | |
- NO OF RESEARCHERS: | 1 | 1 | 1 | |
- NO OF SUPPORTING STAFF: | 3 | 3 | 3 | |
ESTIMATED BUDGET (in Taka): | ||||
- OPERATIONAL EXPENSES: | 310,000 | |||
- CAPITAL EXPENSES: | 170,000 | |||
- TOTAL: | 480,000 |
PROJECT TITLE: | Paddy-cum-shrimp culture | CODE: J-01 |
STATION OF EXECUTION: | RFRS, Chandpur | |
PROGRAMME: | Paddy-cum-fish culture | |
RESEARCH AREA(S): | CODE(S): | |
- Pond production management | 04–10 | |
- Socio-economics | 14–01 |
OBJECTIVES:
TIME SCHEDULE: | ||||
- DATE OF COMMENCEMENT: | 01.09.1986 | |||
- DATE OF COMPLETION: | 31.08.1989 | |||
MANPOWER: | YEAR 1 | YEAR 2 | YEAR 3 | |
- NO OF RESEARCHERS: | 1 | 1 | 1 | |
- NO OF SUPPORTING STAFF: | 2 | 2 | 2 | |
ESTIMATED BUDGET (in Taka): | ||||
- OPERATIONAL EXPENSES: | 250,000 | |||
- CAPITAL EXPENSES: | 220,000 | |||
- TOTAL: | 470,000 |
PROJECT TITLE: | Paddy-cum-fish culture | CODE: J-02 |
STATION OF EXECUTION: | RFRS, Chandpur | |
PROGRAMME: | Paddy-cum-fish culture | |
RESEARCH AREA(S): | CODE(S): | |
- Pond production management | 04–11 | |
- Socio-economics | 14–01 |
OBJECTIVES:
TIME SCHEDULE: | ||||
- DATE OF COMMENCEMENT: | 01.09.1986 | |||
- DATE OF COMPLETION: | 31.08.1989 | |||
MANPOWER: | YEAR 1 | YEAR 2 | YEAR 3 | |
- NO OF RESEARCHERS: | 2 | 2 | 2 | |
- NO OF SUPPORTING STAFF: | 1 | 1 | 1 | |
ESTIMATED BUDGET (in Taka): | ||||
- OPERATIONAL EXPENSES: | 270,000 | |||
- CAPITAL EXPENSES: | 210,000 | |||
- TOTAL: | 480,000 |
PROJECT TITLE: | Toxicity of rice pesticides/fungicides to fish/shrimp | CODE: J-03 |
STATION OF EXECUTION | RFRS, Chandpur | |
PROGRAMME: | Paddy-cum-fish culture | |
RESEARCH AREA(S): | CODE(S): | |
- Health care of freshwater species | 12–03 | |
- Riverine fisheries production management | 06–04 | |
- Pond production management | 04–10/04–11 | |
- Socio-economics | 14-06 |
OBJECTIVES:
TIME SCHEDULE: | ||||
- DATE OF COMMENCEMENT: | 01.10.1986 | |||
- DATE OF COMPLETION: | 30.09.1989 | |||
MANPOWER: | YEAR 1 | YEAR 2 | YEAR 3 | |
- NO OF RESEARCHERS: | 2 | 2 | 2 | |
- NO OF SUPPORTING STAFF: | 2 | 2 | 2 | |
ESTIMATED BUDGET (in Taka): | ||||
- OPERATIONAL EXPENSES: | 330,000 | |||
- CAPITAL EXPENSES: | 105,000 | |||
- TOTAL: | 435,000 |
PROJECT TITLE: | Production ecology of Lake Kaptai | CODE: K-01 |
STATION OF EXECUTION: | RFRS, Chandpur | |
PROGRAMME: | Production in large waterbodies | |
RESEARCH AREA (S): | CODE (S): | |
- Large freshwater bodies production management | 05–01/05–03 | |
- Cage/pen production management | 03–06 | |
- Socio-economics | 14-02/14-06/14-07/14-08 |
OBJECTIVES:
TIME SCHEDULE: | ||||
- DATE OF COMMENCEMENT: | 01.01.1987 | |||
- DATE OF COMPLETION: | 31.12.1989 | |||
MANPOWER: | YEAR 1 | YEAR 2 | YEAR 3 | |
- NO OF RESEARCHERS: | 4 | 4 | 4 | |
- NO OF SUPPORTING STAFF: | 6 | 6 | 6 | |
ESTIMATED BUDGET (in Taka): | ||||
- OPERATIONAL EXPENSES: | 2,550,000 | |||
- CAPITAL EXPENSES: | 950,000 | |||
- TOTAL: | 3,500,000 |
PROJECT TITLE: | Stocking of floodplains | CODE: K-02 |
STATION OF EXECUTION: | RFRS, Chandpur | |
PROGRAMME: | Production in large waterbodies | |
RESEARCH AREA (S): | CODE (S): | |
- Riverine fisheries production management | 06-06 | |
- Large freshwater bodies production management | 05-02 |
OBJECTIVES:
TIME SCHEDULE: | ||||
- DATE OF COMMENCEMENT: | 01.07.1988 | |||
- DATE OF COMPLETION: | 30.06.1991 | |||
MANPOWER: | YEAR 1 | YEAR 2 | YEAR 3 | |
- NO OF RESEARCHERS: | 3 | 3 | 3 | |
- NO OF SUPPORTING STAFF: | 5 | 5 | 5 | |
ESTIMATED BUDGET (in Taka): | ||||
- OPERATIONAL EXPENSES: | 1,000,000 | |||
- CAPITAL EXPENSES: | 400,000 | |||
- TOTAL: | 1,400,000 |
PROJECT TITLE: | Survey of suitable places for pen and cage culture | CODE: L-01 |
STATION OF EXECUTION: | RFRS, Chandpur | |
PROGRAMME: | Pen and cage culture | |
RESEARCH AREA (S): | CODE (S): | |
- Cage/pen production management | 03–01 |
OBJECTIVES:
TIME SCHEDULE: | ||||
- DATE OF COMMENCEMENT: | 01.01.1987 | |||
- DATE OF COMPLETION: | 31.12.1987 | |||
MANPOWER: | YEAR 1 | YEAR 2 | YEAR 3 | |
- NO OF RESEARCHERS: | 1 | - | - | |
- NO OF SUPPORTING STAFF: | - | - | - | |
ESTIMATED BUDGET (in Taka): | ||||
- OPERATIONAL EXPENSES: | 60,000 | |||
- CAPITAL EXPENSES: | - | |||
- TOTAL: | 60,000 |
PROJECT TITLE: | Pen and cage technology | CODE: L-02 |
STATION OF EXECUTION: | RFRS, Chandpur | |
PROGRAMME: | Pen and cage culture | |
RESEARCH AREA(S) | CODE (S): | |
- Cage/pen production management | 03–02/03–03/03–06 | |
- Large freshwater bodies production management | 05–01 | |
- Nutrition and feed | 10-03/10-04 | |
- Socio-economics | 14-01/14-05 |
OBJECTIVES:
TIME SCHEDULE: | ||||
- DATE OF COMMENCEMENT: | 01.01.1987 | |||
- DATE OF COMPLETION: | 31.12.1989 | |||
MANPOWER: | YEAR 1 | YEAR 2 | YEAR 3 | |
- NO OF RESEARCHERS: | 2 | 2 | 2 | |
- NO OF SUPPORTING STAFF: | 2 | 2 | 2 | |
ESTIMATED BUDGET (in Taka): | ||||
- OPERATIONAL EXPENSES: | 730,000 | |||
- CAPITAL EXPENSES: | 600,000 | |||
- TOTAL: | 1,330,000 |
PROJECT TITLE: | Testing of freshwater pen and cage culture systems | CODE: L-03 |
STATION OF EXECUTION: | RFRS, Chandpur | |
PROGRAMME: | Pen and cage culture | |
RESEARCH AREA (S): | CODE (S): | |
- Cage/pen production management | 03–03 | |
- Socio-economics | 14-04 |
OBJECTIVES:
TIME SCHEDULE: | ||||
- DATE OF COMMENCEMENT: | 01.01.1988 | |||
- DATE OF COMPLETION: | 31.12.1989 | |||
MANPOWER: | YEAR 1 | YEAR 2 | YEAR 3 | |
- NO OF RESEARCHERS: | 1 | 1 | - | |
- NO OF SUPPORTING STAFF: | 1 | 1 | - | |
ESTIMATED BUDGET (in Taka): | ||||
- OPERATIONAL EXPENSES: | 350,000 | |||
- CAPITAL EXPENSES: | 50,000 | |||
- TOTAL: | 400,000 |
PROJECT TITLE: | Diet testing of feeds | CODE: M-01 |
STATION OF EXECUTION: | RFRS, Chandpur | |
PROGRAMME: | Nutritional studies | |
RESEARCH AREA(S): | CODE(S): | |
- Nutrition and feed | 10-03/10-04/10-05 | |
- Socio-economics | 14-05 |
OBJECTIVES:
TIME SCHEDULE: | ||||
- DATE OF COMMENCEMENT: | 01.01.1988 | |||
- DATE OF COMPLETION: | 31.12.1989 | |||
MANPOWER: | YEAR 1 | YEAR 2 | YEAR 3 | |
- NO OF RESEARCHERS: | 2 | 2 | - | |
- NO OF SUPPORTING STAFF: | 2 | 2 | - | |
ESTIMATED BUDGET (in Taka): | ||||
- OPERATIONAL EXPENSES: | 480,000 | |||
- CAPITAL EXPENSES: | 120,000 | |||
- TOTAL: | 600,000 |
PROJECT TITLE: | Management practices for mono- and polyculture of Penaeus monodon | CODE: N-01 |
STATION OF EXECUTION: | BFRS, Paikgacha | |
PROGRAMME: | Culture programme | |
RESEARCH AREA(S): | CODE(S): | |
- Brackishwater production management | 02-01/02-03 | |
- Nutrition and feed | 10-04/10-05 |
OBJECTIVES:
TIME SCHEDULE: | ||||
- DATE OF COMMENCEMENT: | 01.08.1988 | |||
- DATE OF COMPLETION: | 31.07.1991 | |||
MANPOWER: | YEAR 1 | YEAR 2 | YEAR 3 | |
- NO OF RESEARCHERS: | 1 | 1 | 1 | |
- NO OF SUPPORTING STAFF: | 2 | 2 | 2 | |
ESTIMATED BUDGET (in Taka): | ||||
- OPERATIONAL EXPENSES: | 600,000 | |||
- CAPITAL EXPENSES: | 200,000 | |||
- TOTAL: | 800,000 |
PROJECT TITLE: | Culture of P. semisulcatus, P. indicus, P. merguiensis and M. monoceros | CODE: N-02 |
STATION OF EXECUTION: | BFRS, Paikgacha | |
PROGRAMME: | Culture programme | |
RESEARCH AREA(S): | CODE(S): | |
- Brackishwater production management | 02-03 | |
- Socio-economics | 14-05 |
OBJECTIVES:
TIME SCHEDULE: | ||||
- DATE OF COMMENCEMENT: | 01.08.1988 | |||
- DATE OF COMPLETION: | 31.07.1991 | |||
MANPOWER: | YEAR 1 | YEAR 2 | YEAR 3 | |
- NO OF RESEARCHERS: | 1 | 1 | 1 | |
- NO OF SUPPORTING STAFF: | 3 | 3 | 3 | |
ESTIMATED BUDGET (in Taka): | ||||
- OPERATIONAL EXPENSES: | 700,000 | |||
- CAPITAL EXPENSES: | 200,000 | |||
- TOTAL: | 900,000 |
PROJECT TITLE: | Management practices for mono-and polyculture of Macrobrachium rosenbergii | CODE: N-03 |
STATION OF EXECUTION: | BFRS, Paikgacha | |
PROGRAMME: | Culture programme | |
RESEARCH AREA(S): | CODE(S): | |
- Brackishwater production management | 02-02/02-03 | |
- Nutrition and feed | 10-04/10-05 |
OBJECTIVES:
TIME SCHEDULE: | ||||
- DATE OF COMMENCEMENT: | 01.01.1988 | |||
- DATE OF COMPLETION: | 31.12.1990 | |||
MANPOWER: | YEAR 1 | YEAR 2 | YEAR 3 | |
- NO OF RESEARCHERS: | 1 | 1 | 1 | |
- NO OF SUPPORTING STAFF: | 2 | 2 | 2 | |
ESTIMATED BUDGET (in Taka): | ||||
- OPERATIONAL EXPENSES: | 600,000 | |||
- CAPITAL EXPENSES: | 200,000 | |||
- TOTAL: | 800,000 |
PROJECT TITLE: | Culture of live food organisms for feeding shrimp larvae | CODE: N-04 |
STATION OF EXECUTION: | BFRS, Paikgacha | |
PROGRAMME: | Culture programme | |
RESEARCH AREA(S): | CODE(S): | |
- Brackishwater production management | 02-03 | |
- Reproduction marine and brackishwater species | 08-05 | |
- Nutrition and feed | 10-03 |
OBJECTIVES:
TIME SCHEDULE: | ||||
- DATE OF COMMENCEMENT: | 01.01.1988 | |||
- DATE OF COMPLETION: | 31.12.1990 | |||
MANPOWER: | YEAR 1 | YEAR 2 | YEAR 3 | |
- NO OF RESEARCHERS: | 1 | 1 | 1 | |
- NO OF SUPPORTING STAFF: | 1 | 1 | 1 | |
ESTIMATED BUDGET (in Taka): | ||||
- OPERATIONAL EXPENSES: | 300,000 | |||
- CAPITAL EXPENSES: | 200,000 | |||
- TOTAL: | 500,000 |
PROJECT TITLE: | Culture of Artemia in salt pans | CODE: N-05 |
STATION OF EXECUTION: | BFRS, Paikgacha | |
PROGRAMME: | Culture programme | |
RESEARCH AREA(S): | CODE(S): | |
- Brackishwater production management | 02–03 | |
- Reproduction marine and brackishwater species | 08-03 | |
- Nutrition and feed | 10-06 |
OBJECTIVES:
TIME SCHEDULE: | ||||
- DATE OF COMMENCEMENT: | 01.04.1988 | |||
- DATE OF COMPLETION: | 31.03.1991 | |||
MANPOWER: | YEAR 1 | YEAR 2 | YEAR 3 | |
- NO OF RESEARCHERS: | 1 | 1 | 1 | |
- NO OF SUPPORTING STAFF: | 2 | 2 | 2 | |
ESTIMATED BUDGET (in Taka): | ||||
- OPERATIONAL EXPENSES: | 400,000 | |||
- CAPITAL EXPENSES: | 200,000 | |||
- TOTAL: | 600,000 |
PROJECT TITLE: | Testing of shrimp feeds | CODE: N-06 |
STATION OF EXECUTION: | BFRS, Paikgacha | |
PROGRAMME: | Culture programme | |
RESEARCH AREA(S): | CODE(S): | |
- Brackishwater production management | 02-01/02-02 | |
- Nutrition and feed | 10-05 |
OBJECTIVES:
TIME SCHEDULE: | ||||
- DATE OF COMMENCEMENT: | 01.01.1988 | |||
- DATE OF COMPLETION: | 31.12.1990 | |||
MANPOWER: | YEAR 1 | YEAR 2 | YEAR 3 | |
- NO OF RESEARCHERS: | 1 | 1 | 1 | |
- NO OF SUPPORTING STAFF: | 2 | 2 | 2 | |
ESTIMATED BUDGET (in Taka): | ||||
- OPERATIONAL EXPENSES: | 250,000 | |||
- CAPITAL EXPENSES: | 100,000 | |||
- TOTAL: | 350,000 |
PROJECT TITLE: | Culture of commercially important brackishwater species other than shrimps | CODE: N-07 |
STATION OF EXECUTION: | BFRS, Paikgacha | |
PROGRAMME: | Culture programme | |
RESEARCH AREA(S): | CODE(S): | |
- Brackishwater production management | 02–03 | |
- Socio-economics | 14/02/14-05 |
OBJECTIVES:
TIME SCHEDULE: | ||||
- DATE OF COMMENCEMENT: | 01.08.1987 | |||
- DATE OF COMPLETION: | 31.07.1990 | |||
MANPOWER: | YEAR 1 | YEAR 2 | YEAR 3 | |
- NO OF RESEARCHERS: | 2 | 2 | 2 | |
- NO OF SUPPORTING STAFF: | 3 | 3 | 3 | |
ESTIMATED BUDGET (in Taka): | ||||
- OPERATIONAL EXPENSES: | 680,000 | |||
- CAPITAL EXPENSES: | 170,000 | |||
- TOTAL: | 850,000 |