(27) The total amount of IDA-money available for civil (construction) work at HQ, FARS and RFRS totals to 144.22 lakh Taka, including contingencies (see section 08).
(23) For FARS the only civil work planned to be carried out from this IDA budget is the construction of a small building for the experimental feed mill, to be bought under the equipment head. An outline for such building, including the services needed, has been prepared in March 1986 by the Fish Nutrition Consultant, and was presented in TA-report No. 04. The building is budgeted as follows:
- 2400 sq. ft. × Taka 400 = (approx.) | Taka 10.00 lakh |
- electricity and water supply, drainage, = 12 % = | 1.20 lakh |
- basic equipment (fridge, freezer, boiler) = | 0.50 lakh |
TOTAL: | Taka 11.70 lakh. |
Purchase of the equipment for the feed mill (approx. US$ 90,000.-) should not start before construction of the feed mill building has actually started.
(29) For the HQ the wishes are as follows:
an administrative building, estimated to cost 110 lakh Taka, including furniture. This building can only partly be paid from IDA-funds and on the basis of savings elsewhere; presently such savings are not clearly found;
residential buildings for the HQ staff. Not yet budgeted; no funding source has been identified as yet.
(30) For RFRS the wishes are as follows:
an experimental pond complex (by reconstruction of an existing complex), estimated to amount to 5.09 lakh Taka;
repair and improvement of the hatchery, estimated to amount to 3 lakh Taka.
(31) Table 7 presents a complete picture of the planned civil works. The total amount of IDA-funds needed is 86.3 lakh Taka, which is 51.1 lakh Taka more than the available 137.4 lakh Taka. Even when 15 lakh Taka are re-allocated to equipment for MFRS, an amount of approximately 36.1 lakh Taka will be saved from the available funds. Together with the 0.2 lakh Taka from equipment savings (62.5 minus 62.3) total savings accumulate to 36.3 lakh Taka.
Table 7 - Budget for civil works at HQ/FARS/RFRS (lakh Taka)
ITEM | IDA-FUNDS | OTHER FUNDS/SOURCE | PRIORITY | ||
HQ | - administrative building | 0.0 | 110.0 | IDA | high |
- residential buildings | 0.0 | …. | ? | medium | |
- auditorium | 0.0 | 33.0 | DANIDA | low | |
FARS | - feed mill building | 11.0 | 0.0 | IDA | high |
RFRS | - experimental pond complex | 5.1 | 0.0 | IDA | high |
- pump-filter system | 0.8 | 0.0 | IDA | high | |
- repair RFRS building | 4.3 | 0.0 | IDA | high | |
- experimental paddy field | 0.0 | 1.5 | ContRes | high | |
- repair/improvement hatchery | 3.0 | 0.0 | IDA | high | |
- boundary wall | 24.6 | 0.0 | IDA | low | |
- repair approach road | 8.8 | 0.0 | IDA | medium | |
- repair residential buildings | 9.6 | 0.0 | IDA | medium | |
- repair guesthouse | 1.5 | 0.0 | IDA | medium | |
- repair jetty | 0.3 | 0.0 | IDA | high | |
- electrification | 8.6 | 0.0 | IDA | low | |
- Rangamati sub-station | 3.0 | 0.0 | IDA | high | |
- drainage facilities | 5.0 | 0.0 | IDA | low | |
TOTAL AMOUNT FOR CIVIL WORKS | 151.7 | …. |
(32) The budget for civil works for BFRS in Paikgacha has been worked out in TA-report No. 13 (BFRS Design), and is in summary presented in the present report in Table 8.
Table 8 - Budget approximations for civil works at BFRS
COMPONENT | QUANTITY | COST | TOTAL, Taka × 1000 | |
1. Land | 70 acres | 75,000 | 5,250 | |
2. Earthworks | ||||
Main supply, wall | 420,000 | |||
Main drain | 40,000 | |||
Secondary supply | 210,000 | |||
Secondary drain | 16,000 | |||
1 ha ponds | 210,000 | |||
0.5 ha " | 330,000 | |||
0.2 ha " | 310,000 | |||
0.1 ha " | 300,000 | |||
Miscellaneous ponds | 160,000 | |||
Building area | 240,000 | |||
Fill material, excavation | 2,000,000 | 4,236 | ||
3. Water control | ||||
Main gate | 360,000 | |||
Pumping station* | 30,000* | * pumps excluded | ||
Secondary gates | 600,000 | (in eqt. budget) | ||
Tertiary gates | 900,000 | |||
Drain outlets | 600,000 | 2,490 | ||
4. Water supply, services | ||||
Saline water | 300,000 | |||
Tubewell | 40,000 | |||
High quality system | 150,000 | |||
Storage tanks | 300,000 | |||
Septic tank | 250,000 | 1,040 | ||
5. Buildings | ||||
Administration | 3,100,000 | |||
Laboratories | ||||
Analytical | 1,900,000 | |||
Toxicology | 1,430,000 | |||
Demonstration | 600,000 | |||
Hatchery | 2,100,000 | |||
Services | 1,200,000 | |||
Rest house | 1,350,000 | |||
Residences | ||||
B | 1,350,000 | |||
C | 2,100,000 | |||
D | 3,400,000 | |||
E | 1,350,000 | |||
F | 4,200,000 | |||
G | 1,250,000 | 25,330 | ||
6. Services | ||||
Electrical, at 8% of (5) | 2,026,000 | |||
Plumbing, at 6% OF (5) | 1,520,000 | |||
Airconditioning, at 5% OF (5) | 1,267,000 | |||
Cold store | 200,000 | 5,013 | ||
7. Site works | ||||
Road, 1000m, at 800/m | 800,000 | |||
Bridges | 400,000 | |||
Wall protection | 100,000 | |||
Fences, huts | 200,000 | |||
Landscaping | 300,000 | 1,800 | ||
TOTAL | 45,159 |
The total amount needed for civil works at BFRS is 451.59 lakh Taka. In this amount is included a GOB contribution of 52.00 lakh Taka for land purchase, and a GOB contribution of 26.36 lakh Taka for construction (as per PP). The remaining needed amount of 373.23 lakh Taka is more than the original IDA contribution from the PP of 263.61 lakh Taka, but it is still within the SAR budget (including contingencies), which amounts to 383.21 lakh Taka.
(33) Table 9 shows the total budgetary picture for BFRS; enough financial space is created by the addition of the 36.3 lakh Taka savings from the other stations.
Table 9 - Renewed budget for BFRS (lakh Taka)
ITEM | NEEDED | AVAILABLE | SOURCE |
- Land purchase | 52.00 | 50.00 | GOB, as per PP; |
2.00 | GOB, savings Chittagong. | ||
- Construction | 399.59 | 26.36 | GOB, as per PP; |
237.25 | IDA, as per PP; | ||
36.30 | IDA, savings other sttns; | ||
99.68 | IDA, contingencies. | ||
- Engineering, 20 % | 20.00 | 20.00 | IDA, contingencies. |
- Equipment, general | 31.30 | 31.30 | IDA, as per PP |
- Equipment, research (estimate) | 26.02 | 6.57 | IDA, as per PP; |
1.25 | IDA, savings furniture; | ||
9.70 | IDA, contingencies; | ||
8.50 | GOB, savings Chittagong. | ||
- CDST (estimate) | 52.25 | 26.37 | GOB, as per PP; |
25.88 | GOB, contingencies. | ||
- Furniture | 10.04 | 10.04 | IDA, as per PP. |
TOTAL IDA FUNDS NEEDED: | 452.09 | lakh Taka. | |
TOTAL GOB FUNDS NEEDED: | 139.11 | lakh Taka. |
(34) The needed IDA funds (452.09 lakh Taka) are covered completely by the budget for BFRS (see section 10), to which the 36.3 lakh Taka savings from HQ/FARS/RFRS are added:
- civil works | 237.25 lakh Taka |
- equipment | 37.87 " " |
- furniture | 11.29 " " |
- contingencies | 129.38 " " |
452.09 lakh Taka. |
(35) The needed GOB funds (139.11 lakh Taka) are covered completely by the GOB budget for BFRS (PP-provision) with addition of 10.50 lakh Taka savings (no procurement of land in Chittagong):
- land procurement | 50.00 lakh Taka |
- savings Chittagong | 10.50 " " |
- civil works | 26.36 " " |
- CDST | 26.37 " " |
- contingencies | 25.88 " " |
139.11 lakh Taka. |