Presently, the some 41 000 km2 of existing African reservoirs (up to 1982) provide about 10 percent of the total 1.4 million ton fish harvest from Africa's inland waters. Recent yields from Africa's largest reservoirs with developed fisheries have ranged from 27 to 65 kg/ha/year with a median yield of 55 kg/ha/year.
The projected increases in reservoir surface area have the potential to make a substantial addition to Africa's inland fishery output. At a conservatively estimated harvest rate of 3.5 t/km2/year (35 kg/ha/year) the additional 24 000 km2 of reservoir area projected for the 1980s could provide 84 000 t, and the 32 000 km2 of new reservoir area projected for the 1990s could add a further 112 000 t by 2000. However, the net increase in fishery yield will be less because of improvement caused losses to downstream river and floodplain fisheries.
These new reservoirs could be made to yield even larger quantities of fish than indicated above; however, to do so will require efficient and early (pre-impoundment) planning for new reservoir fisheries, timely fishery development as reservoir area expands, and well-conceived management of the fisheries as resources come under increasingly heavier exploitation.
Planning
Much useful information has been gained from observations on existing Africa reservoir fisheries, including the results of pre- and post-impoundment applied fishery research, and from management and development activities as the reservoirs have aged (Kapetsky and Petr, 1984). While each new reservoir is unique from an ecological and economic point of view, it is clear that it is generally possible to design and operate hydropower dams to benefit fisheries with little or no economic sacrifice to the efficiency of electricity generation nor inconvenience to other user interests.
Broad guidelines to enable the incorporation of special characteristics in overall dam design favouring both downstream and reservoir fisheries, are now available (e.g., Bernaczek, 1984). However, if such design features are to be adopted, it is necessary for fishery officials to intervene in the planning process at its earliest stages when fundamental dam designs are first conceived.
Similarly, at a later planning stage, once the basic physical characteristics of the future reservoir have been established (e.g., area and depth) along with the geochemistry of the watershed and knowledge of riverine fish fauna, fishery yield potential and general reservoir ecology can be predicted (e.g., Marshall, in press). These predictions can be made with accuracy sufficient for planning for such basic fishery development parameters as numbers of fishermen which the resources can support, quantities and kinds of fishing equipment required, and needs for government services such as health, transportation and education.
With the same basic information, losses to downstream fisheries can be gauged. Again, it is incumbent on fishery officials to ensure that these predictions are generated at the earliest possible moment. Such preliminary predictions can be made well in advance of dam construction (see Marshall, in press, for example), and ideally they should accompany the “system studies” referred to in Section 5.
The broad implications of new reservoirs for national and intra-national fishery organizations are that needs for trained fishery personnel at all levels have to be anticipated and acted upon at once, if the full fishery potential of new reservoirs is to be realized. Just as there are long lags between the planning for hydropower development and bringing it “on stream” so there are similar lags in providing personnel sufficiently trained and experienced to manage and develop reservoir fisheries, whether of administrators, field biologists, or extension workers. One way to ensure that adequately prepared fishery personnel are available when required is to include their training as one of the costs of the hydro-development “package”. Ample justification for such expenditure, from a purely investment point of view, is available from the economic performance of existing African reservoir fisheries as providers of income and employment in fishing, processing, transporting and marketing the catch as well as in boatbuilding, engine maintenance, sales of fishing gears, and other activities economically tied to the fishing industry.
Table 1
Details of known dams and reservoirs to be constructed in 1980–90
Country | Dam | River | Installed capacity- MW | Cost US$ | Irrigation area km2 | Height m | Length m | Volume m3 | Area km2 | Construction schedule | Consultants |
Algeria | Ain Zad | Oued Bou Sellam | - | - | - | 55 | - | 130 m | - | 4 ½ years | W.S. Atkins and Howard Humphries (UK) |
Burundi | Ruzizi IIa Rwegera | Ruzizi Gitenga | 40 18 | 120 m 90 m | - - | - 47 | - 160 | - 13 m | - - | - ?-1986 | Siemens (Germany) |
Botswana | Gaborone | Gaborone | - | 50 m | - | 8 (increase) | 1 800 | 0.03 m (increase) | - | 1983-? | - |
Cameroon | Lagdo Song Lou-lou | Benoue Sanaga | 72 320 | - - | - - | - - | - - | - - | - - | ?-1984 1981–87 | P.R. China EDF (France) |
Egypt | Esna | Nile (167 km below Assuan) | 100 | - | - | - | - | - | - | - | SWECO (Sweden) |
Gabon | Poubara II | Ogooue | 210 | 60 m | - | - | - | - | - | ?-1984 | - |
The Gambia | Yelitenda | Gambia | - | - | - | - | - | - | - | 4 years | Goode and Partners and Peate Marwick and Mitchell |
Ivory Coast | Soubre | Sassandra | 288 | 650 m | - | - | - | - | - | 1984–89 | - |
Kenya | Kiambere | Tana | 140 | 540 m | - | 100 | 1 000 | - | - | 1983–88 | - |
Mali | Manantali | Bafing/Senegal | 240 | 700 m | 2 250 | 70 | 1 500 | - | 447 | 1984–85 | - |
Mauritania | Foum Gleita | Gorgol Noir | - | - | - | 38 | 97 | 510 m | - | 1982-? | Nuovo Castoro (Italy) |
Niger | Kandadji | Niger | 125 | - | 1 400 | 13 | 10 000 | 1 400 m | 250 | - | SOFRELES (France) |
Nigeria | Jebba | Niger | 540 | - | - | 28 | - | - | 303 FSL | 1983–84 | Montreal Eng. (Canada) |
Dadin Kowa | Gongola | - | - | - | - | - | - | 288 FSL | ?-1985 | Montreal Eng. (Canada) | |
Shiroro | Kaduna | 600 | 600 | - | 95 | 640 | 4 400 m | - | ?-1985 | - | |
Senegal | Diama | Senegal | - | - | - | - | - | - | - | ?-1985 | - |
Swaziland | Lupohlo- Ezelwini | - | 20 | 50 m | - | - | - | - | - | ?-1985 | - |
Tanzania | Kidatu- Mtera | Great Ruaha | 80 (add) | 275 m | - | - | - | - | - | 1983-? | - |
Togo/Benin | Nangbeto | Mano | 66 | 210 m | 420 | 48 | 4 900 | 1 700 m | - | ?-1987 | Electrowatt (Sw) and SOGREAH |
Tunisia | Mornoghia | Oued Mornoghia | - | - | - | 30 | 1 400 | 2 m | - | - | Coyne and Bellier (France) |
Total installed capacity | 3 019 MW |
a With Rwanda and Zaire
m - millions
Table 2
Projected hydro supply in MW installed capacity 1980–2000
Country | Hydro potential in MW | Present capacity-MW 1980 | Projected capacity-MW | |
1990 | 2000 | |||
Angola | (23 000) | 533 | 1 000 | 2 800 |
Benin | (500) | - | 30 | 70 |
Burundi | (800) | 11 | 30 | 70 |
Cameroon | (23 000) | 263 | 839 | 1 240 |
Central African Republic | (2 000) | 19 | 33 | 53 |
Congo | (11 000) | 90 | 147 | 247 |
Ethiopia | (12 000) | 216 | 371 | 675 |
Equatorial Guinea | (2 000) | - | 2 | 10 |
Gabon | (18 000) | 137 | 570 | 1 030 |
The Gambia | - | - | 30 | |
Ghana | (2 000) | 792 | 928 | 1 828 |
Guinea | (5 000) | 40 | 190 | 400 |
Guinea-Bissau | (60) | - | 30 | 30 |
Ivory Coast | (3 000) | 614 | 1 202 | 2 400 |
Kenya | (6 000) | 336 | 754 | 1 154 |
Lesotho | (450) | - | - | 100 |
Liberia | (2 000) | 68 | 266 | 694 |
Madagascar | (7 800) | 45 | 148 | 332 |
Malawi | (900) | 101 | 214 | 334 |
Mali | (2 000) | 6 | 76 | 196 |
Mozambique | (15 000) | 2 258 | 3 950 | 4 150 |
Niger | (235) | - | 25 | 100 |
Nigeria | (12 500) | 760 | 2 900 | 4 900 |
Sao Tome and Principe | (50) | 2 | 12 | 18 |
Rwanda | (600) | 12 | 56 | 116 |
Senegal | (500) | - | 200 | 400 |
Sierra Leone | (1 300) | 2 | 72 | 72 |
Somalia | (50) | - | 37 | 37 |
Sudan | (2 700) | 155 | 345 | 865 |
Swaziland | (600) | 20 | 60 | 100 |
Tanzania | (9 500) | 243 | 323 | 623 |
Togo | (270) | - | 30 | 70 |
Uganda | (1 200) | 150 | 150 | 450 |
Upper Volta | (200) | - | 24 | 44 |
Zaire | (120 000) | 1 077 | 2 557 | 2 957 |
Zambia | (12 000) | 1 641 | 2 240 | 5 040 |
Zimbabwe | (3 800) | 633 | 1 233 | 2 900 |
Total | 10 224 | 21 044 | 36 535 |
Table 3
Ratio of installed capacity to reservoir area at some existing sites
Site | Installed capacity in MW | Reservoir area in km2 | Ratio |
Volta | 833 | 8 270 | |
Kariba | 1 266 | 5 550 | |
Kafue/Itezhiteshi | 500 | 4 700 | |
Cabora Bassa | 2 074 | 2 665 | |
Kossou | 174 | 1 600 | |
Kainji | 960 | 1 260 | |
Buyo | 180 | 900 | |
Mtera/Kidatu | 200 | 610 | |
Edea/M'Bakaou/Bamindjin | 263 | 750 | |
Sub-total | 6 450 | 26 305 | 1:4.1 |
Mwadingusha | 69 | 446 | |
Selingue | 48 | 409 | |
Roseires | 210 | 290 | |
Nzilo | 120 | 280 | |
Koka | 34 | 250 | |
Ayame | 50 | 186 | |
Nyumba Ya Mungu | 8 | 180 | |
Sennar | 15 | 160 | |
Massingir | 40 | 151 | |
Khashm el Girba | 10 | 125 | |
Sub-total | 604 | 2 477 | 1:4.1 |
Overall total | 7 054 | 28 782 | 1:4.1 |
Table 4
Most likely hydro projects to year 2000
Country | Project | River | Consultants | Comments |
Angola | - | Cunene | - | Existing projects suspended |
Benin | Nangbeto Mono II | Mono Mono | Electrowatt (Sw) SOGREAH (Fr) SOGREAH (Fr) | See Table 1 Site to be selected |
Burundi | Mulembwe | Electrobel (Be) EDF (Fr) Coyne and Bellier (Fr) | Depends on need for nickel mine Preparing inventory | |
Cameroon | Nachtigal Njock/Mpoume | Sanaga Nyong | EDF - Dafeco (Fr) | Survey of all sites being made |
Central Afr. Republic | Several sites | Lobaye | Sicagri-Electrowatt (Swi) | Several sites |
Congo | Imboulou Sites | Letini Bouenza | Chinese aid | Feasibility study Flow regulation |
Egypt | Quattara-Mogra | SWECO (Swe) | 1 500 MW Quattara dep.req. 15 years to fill | |
Eq. Guinea | Sites | Rio Muni | likely Spanish | |
Ethiopia | Malka-Wakana Gilge Gibe Chimoga | Wabi-Shebelle Blue Nile Omo | Acres (Can) Rep. of Korea Rep. of Korea | 150 MW Staged Dev. of 150 MW Prefeasibility study |
Gabon | Tchimbele II Kingoule (2) Sites | M'Bei M'Bei Ogooue | EDF (Fr) | Feasibility Feasibility Prefeasibility |
The Gambia | Sambangalou | Senegal | Shared with Senegal | |
Ghana | Bui | Black Volta | Snowy Mt. Eng. Corp. (Aust) | 450 MW cost US$ 450 m |
Guinea | Souapiti | Konkoure | Coyne et Bellier Sir Alex Gibb | Preparing water res. master plan |
Guinea Bissau | Saltinho | Corubal | 30 MW site | |
Ivory Coast | Kokumbo | Bandama | EDF (Fr) | System study needed |
Kenya | Turkwell | Tana | Norconsult (Nor) | 100 MW scheduled 1990 |
Lesotho | Highland water sch. | Orange and ash | S. African financed | |
Liberia | V-1 and SP-4 SP-2 | Via St. Paul | US export/import bank | Existing 60 Hz must change to 50 Hz |
Madagascar | Ankorahotra | Vohitra | Motor Columbus (Swi) | Storage for Andekaleka project |
Malawi | Nkula II Kapachira falls | Shire Shire | Unknown | 54 MW and 120 MW or 174 MW total |
Mali | Sotuba Exp. Markala Kenie Tossaye | Niger Niger Niger Niger | EDF-Dafeco (Fr) | Feasibility studies needed |
Mozambique | Cabora Bassa Massingir Mapai | Zambezi Olifantes | 1 525 MW increase 40 MW 60 MW | |
Niger | Kandadji | Niger | SOFRELEC (Fr) | 125 MW complete in 1988 |
Nigeria | Makurdi Ikom Lokoja | Benoue Cross Niger | Motor Columbus (Swi) | Feasibility completed Feasibility underway Problem of flooding villages |
Rwanda | Ruzizi II Rusomo Falls Gihira | Ruzizi Kagera | Tractionel (Bel) Electrobel (Bel) | Complete 1987 Late 1980s (Tanzania) Feasibility completed |
Senegal | Sambangalou | Gambia | Shawinigan (Can) | Feasibility st. needed |
Sierra Leone | Bumbuna Yiben Kongo | Seli Seli Mano | Petrangeli (It) Motor Colomb (Swi) SOFRELEC (Fr) | 305 MW when complete Storage for Bumbuna 150 MW |
Somalia | Fanole Barbera | Juba Juba | 5 MW under construction 32 MW integrated agric. | |
Sudan | Sabaloka Merowe | Nile Nile | Sir Alex Gibb (GB) Merz and McLellan | 120 MW 400–600 MW |
Swaziland | Lupohlo-Ezelwini | 20 MW | ||
Tanzania | Rusomo Falls Stieglers Go. Kingenanas | Kagera Rufiji Kilombero | Acres Int. (Can) | 60 MW with Rwanda 400 MW 150 MW |
Togo | Mono II | Mono | 2nd Proj. on Mono needed | |
Uganda | Ayazo | Nile | 500 MW can be exported | |
Upper Volta | Kompienga Koulbi/Noumbiel Bagre | Kompienga Black Volta White Volta | EDF (Fr) | 14 MW 75 MW (850 km2 reservoir) 10 MW (150 km2 reservoir) |
Zaire | Inga III | Congo | Only small reservoir | |
Zambia | Batoka Mupata | Zambezi Zambezi | Ekono (Fin) | Consultants studying lower needs to 2004 |
Zimbabwe | Batoka Mupata | Zambezi Zambezi | See Zambia - feasib. Studies needed |
Figure 1. Reservoir Area in Africa to the Year 2000