Previous Page Table of Contents Next Page


7. IMPLICATIONS FOR FISHERIES OF NEW RESERVOIRS IN AFRICA

Presently, the some 41 000 km2 of existing African reservoirs (up to 1982) provide about 10 percent of the total 1.4 million ton fish harvest from Africa's inland waters. Recent yields from Africa's largest reservoirs with developed fisheries have ranged from 27 to 65 kg/ha/year with a median yield of 55 kg/ha/year.

The projected increases in reservoir surface area have the potential to make a substantial addition to Africa's inland fishery output. At a conservatively estimated harvest rate of 3.5 t/km2/year (35 kg/ha/year) the additional 24 000 km2 of reservoir area projected for the 1980s could provide 84 000 t, and the 32 000 km2 of new reservoir area projected for the 1990s could add a further 112 000 t by 2000. However, the net increase in fishery yield will be less because of improvement caused losses to downstream river and floodplain fisheries.

These new reservoirs could be made to yield even larger quantities of fish than indicated above; however, to do so will require efficient and early (pre-impoundment) planning for new reservoir fisheries, timely fishery development as reservoir area expands, and well-conceived management of the fisheries as resources come under increasingly heavier exploitation.

Planning

Much useful information has been gained from observations on existing Africa reservoir fisheries, including the results of pre- and post-impoundment applied fishery research, and from management and development activities as the reservoirs have aged (Kapetsky and Petr, 1984). While each new reservoir is unique from an ecological and economic point of view, it is clear that it is generally possible to design and operate hydropower dams to benefit fisheries with little or no economic sacrifice to the efficiency of electricity generation nor inconvenience to other user interests.

Broad guidelines to enable the incorporation of special characteristics in overall dam design favouring both downstream and reservoir fisheries, are now available (e.g., Bernaczek, 1984). However, if such design features are to be adopted, it is necessary for fishery officials to intervene in the planning process at its earliest stages when fundamental dam designs are first conceived.

Similarly, at a later planning stage, once the basic physical characteristics of the future reservoir have been established (e.g., area and depth) along with the geochemistry of the watershed and knowledge of riverine fish fauna, fishery yield potential and general reservoir ecology can be predicted (e.g., Marshall, in press). These predictions can be made with accuracy sufficient for planning for such basic fishery development parameters as numbers of fishermen which the resources can support, quantities and kinds of fishing equipment required, and needs for government services such as health, transportation and education.

With the same basic information, losses to downstream fisheries can be gauged. Again, it is incumbent on fishery officials to ensure that these predictions are generated at the earliest possible moment. Such preliminary predictions can be made well in advance of dam construction (see Marshall, in press, for example), and ideally they should accompany the “system studies” referred to in Section 5.

The broad implications of new reservoirs for national and intra-national fishery organizations are that needs for trained fishery personnel at all levels have to be anticipated and acted upon at once, if the full fishery potential of new reservoirs is to be realized. Just as there are long lags between the planning for hydropower development and bringing it “on stream” so there are similar lags in providing personnel sufficiently trained and experienced to manage and develop reservoir fisheries, whether of administrators, field biologists, or extension workers. One way to ensure that adequately prepared fishery personnel are available when required is to include their training as one of the costs of the hydro-development “package”. Ample justification for such expenditure, from a purely investment point of view, is available from the economic performance of existing African reservoir fisheries as providers of income and employment in fishing, processing, transporting and marketing the catch as well as in boatbuilding, engine maintenance, sales of fishing gears, and other activities economically tied to the fishing industry.

Table 1
Details of known dams and reservoirs to be constructed in 1980–90

CountryDamRiverInstalled capacity-
MW
Cost US$Irrigation area
km2
Height
m
Length
m
Volume
m3
Area
km2
Construction scheduleConsultants
AlgeriaAin ZadOued Bou Sellam---55-  130 m-4 ½ yearsW.S. Atkins and Howard Humphries (UK)
BurundiRuzizi IIa
Rwegera
Ruzizi
Gitenga
  40
  18
120 m
  90 m
-
-
-
47
-
   160
-
     13 m
-
-
-
?-1986
Siemens (Germany)
BotswanaGaboroneGaborone-  50 m- 8 (increase)1 800    0.03 m (increase)-1983-?-
CameroonLagdo
Song Lou-lou
Benoue
Sanaga
  72
320
-
-
-
-
-
-
-
-
-
-
-
-
?-1984
1981–87
P.R. China
EDF (France)
EgyptEsnaNile (167 km below Assuan)100-------SWECO (Sweden)
GabonPoubara IIOgooue210  60 m-----?-1984-
The GambiaYelitendaGambia-------4 yearsGoode and Partners and Peate Marwick and Mitchell
Ivory CoastSoubreSassandra288650 m-----1984–89-
KenyaKiambereTana140540 m-100  1 000--1983–88-
MaliManantaliBafing/Senegal240700 m2 250701 500-4471984–85-
MauritaniaFoum GleitaGorgol Noir---38    97   510 m-1982-?Nuovo Castoro (Italy)
NigerKandadjiNiger125-1 4001310 000   1 400 m250-SOFRELES (France)
NigeriaJebbaNiger540--28--303 FSL1983–84Montreal Eng. (Canada)
Dadin KowaGongola------288 FSL?-1985Montreal Eng. (Canada)
ShiroroKaduna600600-95  6404 400 m-?-1985-
SenegalDiamaSenegal-------?-1985-
SwazilandLupohlo- Ezelwini-  20  50 m-----?-1985-
TanzaniaKidatu- MteraGreat Ruaha80 (add)275 m-----1983-?-
Togo/BeninNangbetoMano  66210 m420484 9001 700 m-?-1987Electrowatt (Sw) and SOGREAH
TunisiaMornoghiaOued Mornoghia---301 400       2 m--Coyne and Bellier (France)
 Total installed capacity3 019 MW        

a With Rwanda and Zaire
m - millions

Table 2
Projected hydro supply in MW installed capacity 1980–2000

CountryHydro potential in MWPresent capacity-MW
1980
Projected capacity-MW
  1990  2000
Angola(23 000)      533  1 000  2 800
Benin     (500)-       30       70
Burundi     (800)        11       30       70
Cameroon(23 000)     263     839  1 240
Central African Republic  (2 000)        19       33       53
Congo(11 000)        90     147     247
Ethiopia(12 000)     216     371     675
Equatorial Guinea  (2 000)-         2       10
Gabon(18 000)     137     570  1 030
The Gambia --       30
Ghana   (2 000)     792     928  1 828
Guinea   (5 000)       40     190     400
Guinea-Bissau       (60)-       30       30
Ivory Coast   (3 000)     614  1 202  2 400
Kenya   (6 000)     336     754  1 154
Lesotho     (450)--     100
Liberia   (2 000)       68     266     694
Madagascar   (7 800)       45     148     332
Malawi     (900)     101     214     334
Mali   (2 000)         6       76     196
Mozambique(15 000)  2 258  3 950  4 150
Niger     (235)-       25     100
Nigeria(12 500)   760  2 900  4 900
Sao Tome and Principe       (50)       2       12       18
Rwanda     (600)     12       56     116
Senegal     (500)-    200     400
Sierra Leone   (1 300)        2       72       72
Somalia       (50)-       37       37
Sudan   (2 700)     155     345     865
Swaziland     (600)       20       60     100
Tanzania   (9 500)     243     323     623
Togo     (270)-       30       70
Uganda   (1 200)     150     150     450
Upper Volta     (200)-       24       44
Zaire(120 000)  1 077   2 557  2 957
Zambia(12 000)  1 641   2 240  5 040
Zimbabwe  (3 800)          633         1 233     2 900  
Total 10 22421 04436 535

Table 3
Ratio of installed capacity to reservoir area at some existing sites

SiteInstalled capacity in MWReservoir area in km2Ratio
Volta   8338 270 
Kariba1 2665 550 
Kafue/Itezhiteshi   5004 700 
Cabora Bassa2 0742 665 
Kossou   1741 600 
Kainji   9601 260 
Buyo   180   900 
Mtera/Kidatu   200   610 
Edea/M'Bakaou/Bamindjin   263   750 
           Sub-total6 45026 305  1:4.1
Mwadingusha     69   446 
Selingue     48   409 
Roseires   210   290 
Nzilo   120   280 
Koka     34   250 
Ayame     50   186 
Nyumba Ya Mungu       8   180 
Sennar     15   160 
Massingir     40   151 
Khashm el Girba     10   125 
           Sub-total   604 2 4771:4.1
           Overall total7 05428 782  1:4.1

Table 4
Most likely hydro projects to year 2000

CountryProjectRiverConsultantsComments
Angola-Cunene-Existing projects suspended
BeninNangbeto

Mono II
Mono

Mono
Electrowatt (Sw)
SOGREAH (Fr)
SOGREAH (Fr)
See Table 1

Site to be selected
BurundiMulembwe Electrobel (Be)
EDF (Fr)
Coyne and Bellier (Fr)
Depends on need for nickel mine
Preparing inventory
CameroonNachtigal Njock/MpoumeSanaga NyongEDF - Dafeco (Fr)Survey of all sites being made
Central Afr. RepublicSeveral sitesLobayeSicagri-Electrowatt (Swi)Several sites
CongoImboulou
Sites
Letini
Bouenza
Chinese aidFeasibility study
Flow regulation
EgyptQuattara-Mogra SWECO (Swe)1 500 MW Quattara dep.req. 15 years to fill
Eq. GuineaSitesRio Munilikely Spanish 
EthiopiaMalka-Wakana
Gilge Gibe
Chimoga
Wabi-Shebelle
Blue Nile
Omo
Acres (Can)
Rep. of Korea
Rep. of Korea
150 MW
Staged Dev. of 150 MW
Prefeasibility study
GabonTchimbele II
Kingoule (2)
Sites
M'Bei
M'Bei
Ogooue
EDF (Fr)Feasibility
Feasibility
Prefeasibility
The GambiaSambangalouSenegal Shared with Senegal
GhanaBuiBlack VoltaSnowy Mt. Eng. Corp. (Aust)450 MW cost US$ 450 m
GuineaSouapitiKonkoureCoyne et Bellier Sir Alex GibbPreparing water res. master plan
Guinea BissauSaltinhoCorubal 30 MW site
Ivory CoastKokumboBandamaEDF (Fr)System study needed
KenyaTurkwellTanaNorconsult (Nor)100 MW scheduled 1990
LesothoHighland water sch.Orange and ash S. African financed
LiberiaV-1 and SP-4 SP-2Via St. PaulUS export/import bankExisting 60 Hz must change to 50 Hz
MadagascarAnkorahotraVohitraMotor Columbus (Swi)Storage for Andekaleka project
MalawiNkula II
Kapachira falls
Shire
Shire
Unknown54 MW and 120 MW or 174 MW total
MaliSotuba Exp.
Markala
Kenie
Tossaye
Niger
Niger
Niger
Niger
EDF-Dafeco (Fr)Feasibility studies needed
MozambiqueCabora Bassa
Massingir
Mapai
Zambezi
Olifantes
 1 525 MW increase
    40 MW
    60 MW
NigerKandadjiNigerSOFRELEC (Fr)  125 MW complete in 1988
NigeriaMakurdi
Ikom
Lokoja
Benoue
Cross
Niger
Motor Columbus (Swi)Feasibility completed
Feasibility underway
Problem of flooding villages
RwandaRuzizi II
Rusomo Falls
Gihira
Ruzizi
Kagera
Tractionel (Bel)
Electrobel (Bel)
Complete 1987
Late 1980s (Tanzania) Feasibility completed
SenegalSambangalouGambiaShawinigan (Can)Feasibility st. needed
Sierra LeoneBumbuna
Yiben
Kongo
Seli
Seli
Mano
Petrangeli (It)
Motor Colomb (Swi)
SOFRELEC (Fr)
305 MW when complete
Storage for Bumbuna
150 MW
SomaliaFanole
Barbera
Juba
Juba
 5 MW under construction
32 MW integrated agric.
SudanSabaloka
Merowe
Nile
Nile
Sir Alex Gibb (GB)
Merz and McLellan
120 MW
400–600 MW
SwazilandLupohlo-Ezelwini  20 MW
TanzaniaRusomo Falls
Stieglers Go.
Kingenanas
Kagera
Rufiji
Kilombero
Acres Int. (Can)60 MW with Rwanda
400 MW
150 MW
TogoMono IIMono 2nd Proj. on Mono needed
UgandaAyazoNile 500 MW can be exported
Upper VoltaKompienga
Koulbi/Noumbiel
Bagre
Kompienga
Black Volta
White Volta
EDF (Fr)14 MW
75 MW (850 km2 reservoir)
10 MW (150 km2 reservoir)
ZaireInga IIICongo Only small reservoir
ZambiaBatoka
Mupata
Zambezi
Zambezi
Ekono (Fin)Consultants studying lower needs to 2004
ZimbabweBatoka
Mupata
Zambezi
Zambezi
 See Zambia - feasib.
Studies needed

Figure 1. Reservoir Area in Africa to the Year 2000

Figure 1

Previous Page Top of Page Next Page