Aquaculture/Hatchery Expert
To advise on detailed engineering/design of the “Beymelek Lagoon Aquaculture Centre”, in close collaboration with the National Project Coordinator, local engineering staff, and hydraulic engineering expert.
To prepare in own office a detailed list and specifications of equipment to be imported, and in particulary to advise on the order of equipment to be purchased by F.A.O. (see UNDP contribution).
To prepare in own office full data, specifications, costings and documents needed for detailed engineering, design and costing of the Centre.
To assist in Antalya (Turkey), local staff (engineering, experts, draftsmen, etc.), in preparing final detailed drawings, specifications, bill of quantities and budget costings needed for the construction of the Centre.
To prepare a final report.
Hydraulic Engineering Expert
To advise on detailed engineering/design on the following work of the “Beymelek Lagoon Aquaculture Centre”, according to the specifications of the aquaculture expert: sea dikes for water inlets and lagoon outlets, brackishwater intake, water channels, concrete tanks and earth ponds complete with water inlet/outlet works and the fish barrier at the lagoon outlet.
To prepare in own office full data, specifications, documents and costings needed for detailed engineering and design of the above-mentioned work.
To assist in Antalya (Turkey), local staff (engineers, experts, draftsmen, etc.), in preparing final detailed drawings, specifications, bill of quantities and budget costings needed for the construction of the Centre.
To give the necessary input for a final report to be prepared by the aquaculture/hatchery expert.
R. Vétillart
6 November 1988
Departure from France. Arrival in Ankara.
L. Berg
7 November 1988
Departure from Italy. Arrival in Ankara.
8 November 1988
Meeting at F.A.O. offices, Ankara with Mr P. Rosenegger and Mr
J.L. Bock (F.A.O.), Mr A. Açara (State Planning Organization) and
Mr Coskun (Ministry of Agriculture).
Meeting at U.N.D.P. office, Ankara with Mr W. Holzhausen
(U.N.D.P.), Mr P. Rosenegger and Mr J.L. Bock.
Departure from Ankara. Arrival in Antalya.
9–11 November 1988
Preliminary meetings at the Provincial Directorate of the
Ministry of Agriculture, Antalya, with Mr S. Evren (Director), O.
Atila (Project Coordinator) and engineers involved in the project
implementation.
Meeting at KEPEZ, Freshwater Aquaculture Station, Antalya, with
Mr R. Bulca (Director).
12–14 November 1988
Survey on project site for coordination of pedological and
topographical surveys and discussion with lagoon specialist Mr R.
Guidastri on fish barrier, Aquaculture Center and lagoon.
15–25 November 1988
Organization and coordination of design carried out by the
Turkish engineers. Provision of basic drawings and
specifications.
Meeting at the Regional Directorate of Harbours with Mr S.
Köseglu (Director) and engineers involved in the detailed design.
Meeting at the Provincial Directorate of Rural Affairs (Min.
Agric.) with Mr U. Sorguç (Director) and engineers.
26–29 November 1988
Survey on project site. Coordination of topographical survey.
30 November – 10 December 1988
Completion of the mission on provision to Turkish engineers of
full specifications for detailed design.
11 December 1988
Departure from Antalya. Arrival in Ankara.
12 December 1988
Meeting at the Ministry of Agriculture, Ankara, with:
Min. Agric.: Mr H. Ögüt (Director General), Mr S. Keskin (Deputy Director General), Mr S. Sabaz, Mr. A. Eryilmaz, Mr I. Dabak and Mr F. Caskun (Heads of Dept.), Mr M. Getmer (Engineer)
- S.P.O.: Mr A. Açara
- F.A.O.: Mr P. Rosenegger and Mr J.L. Bock
- U.N.D.P.: Ms S. Saylan
12–14 December 1988
Meetings at F.A.O. offices, Ankara with representatives of pumps
and generators manufacturers:
15 December 1988
Departure from Ankara. Arrival in Rome.
16 December 1988
Debriefing in Rome
17 December 1988
Departure from Rome.