Following previous mission, to review and complete (if necessary) the final documents prepared by the Turkish engineers and make sure that they are suitable for the farm construction and equipment orders:
Detailed working drawings;
Conditions of contracts (specifications), in particular to check the conditions of carrying out special works:
Other buildings
Specifications for equipment orders.
At the end of the assignment to prepare a report on main findings and recommendations.
R. Vétillart
19 February 1989
Departure from France. Arrival in Rome
20 February
Departure from Rome. Arrival in Antalya
L. Berg
20 February
Departure from Milan. Arrival in Antalya
L. Berg and R. Vétillart
21–24 February
Office work at the Provincial Directorate of the Ministry of
Agriculture (Antalya), meetings with National Project Coordinator
(O. Atila) and engineers involved in project design.
25–26 February
Survey on project site with J.L. Bock (F.A.O., Ankara), meeting
with President of Fishermen Cooperative, G. Kusakci
26 February - 4 March
Office work at the Ministry of Agriculture (Antalya), to complete
revision and final specifications of detailed design.
5 March
Departure from Antalya. Arrival in Ankara
6 March
Office work in F.A.O. office, Ankara. Meeting at the Ministry of
Agriculture with:
Representative of F.A.O., J.L. Bock
7 March
Office work in F.A.O. offices, Ankara and meeting with A. Açara,
F. Coskun, O. Atila, S. Saylan and J.L. Bock.
L. Berg
8 March
Departure from Ankara. Arrival in Rome
8–10 March
Debriefing in F.A.O. Head Quarters
10 March
Departure from Rome. Arrival in Venice
11–19 March
Office work in Padova
R. Vétillart
9 March
Departure from Ankara. Arrival in Rome
10 March
Debriefing in F.A.O. Head Quarters
11 March
Departure from Rome. Arrival in France
1. TOPOGRAPHIC PLANS
1.1.1 Topographic plan (eliminated) 1:2.000
1.1.2 Topographic plan 1:1.000
2. GENERAL PLAN OF THE FARM
2.1.1 General plan
3. WATER INLET FACILITIES
3.1 MAIN CHANNELS
3.1.1A Water inlet channels. Transversal cuts
3.2 SEA WATER RESERVOIR
3.2.1A Sea water reservoir. Cut
4. REARING TANKS AND PONDS
4.1 INTENSIVE REARING TANKS AND CHANNEL
4.1.1A General plan
4.1.2A Longitudinal and transversal cuts
4.1.3A Plans and transversal cuts
4.1.4 Construction details
4.2 SEMI-INTENSIVE REARING PONDS AND CHANNELS
4.2.1 General cuts (eliminated)
4.2.2 Transversal cuts
4.3 BROODSTOCK PONDS
4.3.1A General plan and cut
5. OTHER WATER CHANNELS
5.1 WATER SUPPLY CHANNELS
5.1.1A Channel to intensive rearing tanks. Plans and cuts
5.1.2A Channels to semi-intensive rearing and broodstock
ponds (start from pumping station). Plan
5.1.3 Concrete channels: construction details
5.2 WATER DISCHARGE CHANNELS
5.2.1A Channels from intensive and semi-intensive rearing
tanks and ponds. Transversal cuts.
5.2.2A Channel from intensive rearing tanks: siphon
6. TAIL PONDS
6.1 SETTLING POND
6.1.1A Plan and cut
6.2 LAGOONING POND (HATCHERY)
6.2.1A Cut
7. MONKS
7.1 WATER SUPPLY MONKS
7.1.1A Monks (types A1, A2, A3). Plans and cuts
7.2 WATER DISCHARGE MONKS
7.2.1A Monks (types E1, E2, E3, E4). Plans and cuts
8. LAGOON FISH BARRIER
8.1.1 General plan and cuts
8.1.2 Construction details
9. SEA WORKS (DIKES)
9.1 SEA WATER INTAKE
9.1.1A Plan
9.1.2A Cuts
9.2 LAGOON-SEA COMMUNICATION
9.2.1A Plan
9.2.2A Cuts
10. BRACKISHWATER INTAKE
10.1.1. Water intake and level regulator. Plan and cuts
11. WATER PUMPING/MIXING STATION
11.1.1A Plan and trasversal cut
11.1.2A Longitudinal cut
11.1.3A Construction details
12. ELECTRIC/GENERATOR STATION
12.1 CIVIL ENGINEERING
12.1.1A Plan and cut
12.1.2 Construction details: plan
12.1.3 Construction details: platform and pillars
12.1.4 Construction details: roof
12.1.5 Construction details: fuel tanks
12.2 ELECTRIC PLANT
12.2.1 E1 General lighting system
12.2.1 E2 General panels: details
12.2.1 E3 Control boards TA1-TA2: details
13. HATCHERY
13.1 CIVIL ENGINEERING
13.1.1A General plan
13.1.2A Transversal and longitudinal cuts
13.1.3 Construction details: platform
13.1.4 Construction details: pillars basis
13.1.5 Construction details: roof support
13.1.6 Construction details: spawning unit ceiling
13.1.7 Construction details: laboratory floor
13.1.8 Construction details: spawning unit floor
13.1.9 Construction details: laboratory ceiling
13.1.10 Construction details: roof
13.1.11 Construction details: roof
13.1.12 Construction details: draining system
13.2 ELECTRIC PLAN
13.2.1A General lighting plan
13.2.1 E2 General outlet plan
13.2.1 E3 TT1, TT2 boards/cables: detailed plan
13.2.1 E4 TT3, TT4 boards/cables: detailed plan
13.2.1 E5 TT5, TT6 boards/cables: detailed plan
13.2.1 E6 TT7, TT8 boards/cables: detailed plan
13.2.1 E7 General board/cables: detailed plan
13.2.1 E8 Alarm system: detailed plan
13.2.1 E9 Transversal and longitudinal cuts
13.3 HEATING/CONDITIONING/FRESHWATER SYSTEMS
13.3.1 IS1 Heating system plan
13.3.1 IS2 Heating system scheme
13.3.1 IS3 Heat exchangers system plan
13.3.1 IS4 Heat exchangers system: functional plan
13.3.1 IS5 Boilers system plan
13.3.2 Conditioning system plan
13.3.3 Freshwater/Hot water/Wastewater and air compressor
systems plan
13.4 PIPING SYSTEM
13.4.1 SB1 Water piping systems. Plan
13.4.1 SB2 Water piping systems: details
13.4.1 SB3 Water piping systems: details
13.4.1 SB4 Water piping systems: details
13.4.2 Air/oxygen piping systems. Plan
13.5 OUTDOOR FACILITIES
13.5.1A General plan and detailed plans and cuts
13.5.2A Sea water intake. Plan and cut
13.5.3A Brackishwater intake. Plan and cut
13.5.4 Construction details
13.6 EQUIPMENT
13.6.1 Fiberglass tanks
14. SERVICE BUILDING
14.1 CIVIL ENGINEERING
14.1.1 General plan
14.1.2 Construction details: platform
14.1.3 Construction details: floor
14.1.4 Construction details: ceiling
14.1.5 Construction details: pillars basis
14.1.6 Construction details: roof
14.2 ELECTRIC PLANT
14.1.1 E1 General plan
14.2.1 E2 Detailed plan
14.3 CONDITIONING/FRESHWATER SYSTEMS
14.3.1 Freshwater/Wastewater systems plans
14.3.2 Conditioning/Cool stores systems plans
15. GENERAL DEVICES
15.1 FRESHWATER SYSTEM
15.1.1 General plan
15.2 OUTDOOR ELECTRIC SYSTEMS
15.2.1 Lightning conductor system
15.2.2 E1 Outdoor lighting systems plan
15.2.2 E2 Outdoor lighting detailed plans
15.2.3 Electric system plan for intensive rearing sector
APRIL | MAY | JUNE | JULY | AUGUST | SEPTEMBER | OCTOBER | NOVEMBER | DECEMBER |
1989 | ![]() |
Calculated Cost 1988 (π × 1000) | Inflation rate (1) (%) | Estimated G.O.T. contribution 1989 | |||
in local currency (π × 1000) | in foreign currency (USD) | ||||
A. WORKS | |||||
A.1 | Sea dikes for water inlet | 259.000 | 60 | 414.400 | |
A.2 | Earth Works | 41.000 | 60 | 65.600 | |
A.3 | Generator building | 26.000 | 60 | 41.600 | |
A.4 | Generator installation | 42.000 | 20 | 59.000 | |
A.5 | Electric line + connections | 46.000 | 60 | 74.000 | |
A.6 | Hatchery building + indoor sys. | 418.400 | 60 | 669.500 | |
SUB TOTAL A | 832.400 | 1.315.100 | |||
B. EQUIPMENT | |||||
B.1 | Hatchery (Imported) (2) | 290.000 | |||
B.2 | Hatchery (purchased locally) | 182.000 | 60 | 291.000 | |
B.3 | Generator (imported) | 64.000 | |||
B.4 | Directorate build. (furniture) | 40.000 | 30 | 52.000 | |
SUB TOTAL B | 222.000 | 343.000 | 354.000 | ||
TOTAL | 1.054.400 | 1.658.100 | 354.000 |
(1) Estimated 10 % for month
(2) In addition to UNDP contribution equipment (USD 112.000)
This revised list is aiming to the establishment of the hatchery with a 50% production capacity, ready for operation at the end of 1989, according to the priority work plan proposed.
Equipment specification | Quant. | Unit price | Total cost for 50% cap. | Total cost for 100% cap. |
Imported (in U.S.D.) | ||||
1. U.V. sterilizers | 2 | 22.600 | 45.200 | 104.000 |
2. Hatchery pumps | 49.500 | 88.500 | ||
3. Filters | ||||
- gravel filter | 1 | 17.700 | 17.700 | 35.400 |
- diatom filter | 2 | 2.900 | 5.800 | 8.700 |
4. Air blowers | 4 | 3.000 | 12.000 | 12.000 |
5. Piping (PVC) | 25.000 | 50.000 | ||
6. Special equipment | 10.000 | 20.000 | ||
7. Generator (non-automatic) | 1 | 30.000 | 94.000 | |
8. Laboratory equipment | 5.000 | 35.500 | ||
9. Miscellaneous | 13.000 | 26.500 | ||
TOTAL | USD | 213.200 | 474.600 | |
Purchased Locally (in π × 1000) | ||||
- Fiberglass tanks | 60.000 | 100.000 | ||
- Refrigerators/freezers | 5.000 | 10.000 | ||
- Furniture | 15.000 | 20.000 | ||
- Glassware | 10.000 | 10.000 | ||
- Consumables | 20.000 | 20.000 | ||
- Homogenizer/Grinder | 5.000 | 5.000 | ||
- Tools | 1.000 | 2.000 | ||
- Miscellaneous | 29.800 | |||
TOTAL | π × 1000 | 145.800 | 167.000 |
It is assumed that the costs for the establishment of the sea dikes for the inlet water channel (approx. 415 Mill. π) will be covered by a special budget, allocated directly to the Ministry of Transport, Harbour Directorate of Antalya.
Work specification | Expected Implementation date | Total cost (estimated 89 in π × 1000) |
1. Earth works for inlet channel, water reservoir and hatchery platform. | May-August 1989 | 65.600 |
2. Electric supply systems and generator installation | Sept.-Oct. 1989 | 99.000 |
3. Hatchery construction (civil works) | May-Oct. 1989 | 496.000 |
4. Hatchery electric plant | Sept.-Oct. 1989 | 93.000 |
5. Heating/freshwater plants | Sept.-Oct. 1989 | 73.000 |
TOTAL | π × 1000 | 826.600 |
(π × 1000) | Budget available | Total cost |
A. EQUIPMENT | ||
- Ministry Agric 420 Mill. π - 11.5 % | 372.000 | |
- UNDP Equiv. 100.000 USD | 200.000 | |
TOTAL | 572.000 | |
- Imported equipment Equiv. 213.200 USD | 426.400 | |
- Local Equipment | 145.800 | |
TOTAL | 572.200 | |
Balance A | 0.000 | |
B. WORKS | ||
- 650 Mill. π - 11.5 % | 575.200 | |
- Work costs | 826.600 | |
Balance B | - 251.400 | |
TOTAL BALANCE | -251.400 |
1989 | 1990 | 1991 | |
HATCHERY | ******* | **** | |
SEA DIKES (WATER INTAKE) | **** | ||
SEA WATER INLET CHANNEL | **** | ||
SEA WATER RESERVOIR | **** | ||
GENERATOR STATION | **** | ||
BRACKISHWATER INTAKE | **** | ||
BRACKISHWATER CHANNEL | **** | ||
PUMPING STATION | ***** | ||
INTENSIVE REARING SECTOR | ******* | ||
SEMI-INTENSIVE R. SECTOR | ********* | ||
PERSONNEL/TRAINEE BUILDINGS | ******* | ||
SERVICE BUILDING | ***** | ||
FISH BARRIER | **** | ||
LAGOON-SEA COMMUNICATION | ***** |
Costs have been calculated by Turkish Engineers, on the basis of end 1988 prices
In brackets : estimated costs (under calculation)
1. SEA DIKES | (T.L. × 1.000) |
- for inlet channel | 258.600 |
- for lagoon outlet | 139.800 |
SUB TOTAL 1 | 398.400 |
2. EARTH WORKS | |
SUB TOTAL 2 | (430.000) |
3. CONCRETE WORKS | |
- Pumping/mixing station | 38.000 |
- Intensive rearing sector + channels | 650.000 |
- Hatchery outdoor facilities | 160.000 |
- Fish barrier | (30.000) |
- Monks | 36.800 |
- Brackishwater inlet regulator | 5.000 |
- Bridges/syphons, others | (50.000) |
SUB TOTAL 3 | 969.800 |
4. HATCHERY | |
- Civil works | 310.000 |
- Electric | 57.900 |
- Thermic/conditioning/fresh water | 60.400 |
- Equipment (excluding UNDP contribution) | 762.000 |
SUB TOTAL 4 | 1.190.300 |
5. TECHNICAL SERVICE BUILDING | |
- Civil Works | 54.700 |
- Electric System | 8.600 |
- Thermic/conditioning/piping systems | 53.200 |
- Equipment | 46.500 |
SUB TOTAL 5 | 163.000 |
6. ELECTRIC PLANTS | |
- Electric/generators station (civil works) | 26.200 |
- Supply systems | 24.900 |
- Generators | 176.400 |
- Outdoor lighting system | 121.200 |
- Lightning conductor system | 2.000 |
- Intensive rearing sector system | 29.400 |
- Others | 10.000 |
SUB TOTAL 6 | 390.100 |
7. FARM EQUIPMENT | |
- Pumps | 410.000 |
- Piping | (20.000) |
- Feeders | (96.000) |
- Grates | (5.000) |
- Vehicles | (192.000) |
- Data Aquisition System (hatchery) | (35.000) |
- Miscellaneous | (18.500) |
SUB TOTAL 7 | 776.500 |
8. GENERAL DEVICES | |
- Freshwater system | 6.300 |
- Draining system | (10.000) |
- Roads | (50.000) |
SUB TOTAL 8 | 66.300 |
9. CONTINGENCIES | |
- 10 % | |
SUB TOTAL 9 | 438.440 |
TOTAL | 4.822.800 |
U.V. lamps.
flow capacity: minimum 14 m3/h
dosage efficiency: 24 mJ/cm2 min., penetration factor: 0.8
stainless steel or plastic materials exclusively
manual cleaning system of the U.V. lamp
dosage measurement system
working time recorder
complete electric board
No. 2
Pumps
submersible electric pumps
stainless steel. (AISI 316)
minimum flow: 45 m3/h; head: 6 m No. 3
" " : 21 m3/h; head: 30 m No. 2
vertical plastic pumps
minimum flow: 10 m3/h; head: 12 m No.3
Diatom filter
AISI 304 stainless steel body, epoxy coated and PP
operating pressure: minimum: 1 atm
maximum: 2.5 atm
maximum flow: 10 m3/h
filtering surface: 1.6 m2
pressure control system equipped with self-cleaning candles
filtering material: diatom powder
No. 2
200 Kg of diatom powder
1 Gravel filter
CULLIGAN ITALIANA Spa
Via Gandolfi, 6
40057 CADRIANO DI GRANAROLO (BO), Italy
Tel. (0)51 766614
Fax (0)51 765032
Tlx 510330 CUIT
Model: UF 60 No: 1
Characteristics:
water volume treated: 27.3 m3/h minimum
52.2 m3/h maximum
counter washing volume: 61.3 m3/h
maximum head lost: 1 atm
dimension: (1500 × 1760 × 2210) mm
weight: shipment 3550 Kg
working 5000 Kg
2. Air blowers
To be purchased in Turkey.
SIEMENS
Model: 2BH61 10-OHC22-5 (in Italy) No: 4
Characteristics:
flow: 140 to 258 m3/h; pressure difference: 0,28 to 0,1 bar
3 Kw; 220/380 V; 50 Hz
Accessories:
filter, pressure regulating valve, muffler and flanges
3. Tank vacuum cleaners
POMPEO CATELLI
via Roma, 55
22029 UGGIATE (CO), Italy
Tel. (0) 31 948737
Tlx. 300484 att. Pompeo Catelli
Model: fry tank cleaner No. 2
4. Biofilter foam
IMAR Spa
Via Trieste, 51
35035 MESTRINO (PD), Italy
Tel. (0)49 9000252
Fax (0)49 9000257
Characteristics:
FILTREN T 10: reticulated polyurethane foam
density (ISO 845): 20 – 24 Kg/m3
compression resistance (CDH at 40%): 3 – 5
ultimate elongation (ER %): > 100
tensile strenght (RR kPa): > 60
tear resistance (TR N/cm): > 6
porosity (pores per inch): 7 – 15
dimensions: (900 × 1260 × 125) mm No. 15 pieces
5. Generator
See offers already collected. CATERPILLAR is the most reliable and with best offer.
OTHER SUPPLIERS
(see equipment lists prepared by engineers, Antalya)
PVC material and fittings
P.M. snc di PEVERATI Mario
Via A. Toscanini, 26
44100 FERRARA, Italy
Tel (0)532 94452, 92300
Fax (0)532 92300
Heating/conditioning equipment
DITTA CIPRIANI SCAMBIATORI S.R.L.
Via 25 Aprile
37020 CORRUBBIO (VR)
Tel (0)45 7725466
Fax (0)45 7725530
Electric equipment
IMER Materiale Elettrico Spa
Via delle Industrie, 88
48100 RAVENNA
Tel (0)544 35544
Fax (0)544 39888
Tlx 550858 IMER-I
The Senior Aquaculture Advisor will have:
to prepare a short report on main findings and recommendations.
A. PERSONNEL
A1. Coordination
Senior Aquaculture Advisor (F.A.O.), Ruggero Guidastri
A2. Aquaculture Technical Staff (KEPEZ)
Duygu Turgut
A3. Construction Supervision
1 mechanical engineer
A4. Other Personnel
2 drivers
B. MAIN EQUIPMENT AND FACILITIES
B1. Living Facilities
Living facilities for 1–2 watchmen (existing prefabricate building)
B2. Offices
2–3 offices equipped with telephone, fax and typewriter (Directorate building)
B3. Equipment
a walkye-talkye system
M/M | 1988 | UNTIL MARCH 1989 | AFTER MARCH 1989 | 1990 | 1991 | TOTAL |
1) AQUACULTURE/HATCHERY | 3.5 | 1 (*) | - | - | - | 4.5 |
2) HYDRAULIC ENGINEERING | - | 1 (*) | - | - | - | 4 |
3) LAGOON | 0.75 | - | - | 0.75 | 0.5 | 2 |
4) FRY COLLECTION | - | - | - | 1 | 1 | 2 |
5) PLANCTON CULTURE | - | - | 2 | - | - | 2 |
6) NUTRITION | - | - | - | 1.5 | - | 1.5 |
7) PATHOLOGY | - | - | - | 1 | - | 1 |
8) SENIOR ADVISOR (+) | - | - | 7 | 11 | - | 18 |
9) HATCHERY SPECIALIST | - | - | 2 | 4 | - | 6 |
TOTAL | 7.25 | 2 | 11 | 19.25 | 1.5 |
(*) Additional: these 2M/M were not planned at the time of the meeting of Nov. 8,1988
(+) Including mission of assistance to coordination and construction supervision