Previous Page Table of Contents Next Page


Project 3.0 - Establishment of a National Parks/Protected Areas System

PRIORITY AREA

Conservation of Forest Ecosystems

DURATION

3 years

LOCATION

Wallings, Dark Wood, Gaynors, Great Bird Island, Goat Island (Barbuda), Bird Sanctuary (Codrington Lagoon, Barbuda).

TARGET BENEFICIARIES

Nationals and Tourists

IMMEDIATE OBJECTIVES:

To plan and establish a system of nature reserves, sanctuaries and protected areas including mangroves for conservation of biodiversity, public education regarding the natural environment and ecotourism development.

ACTIVITIES

1. Gazetting of proposed sites and buffer zones.

2. Field surveys and data collection.

3. Classification and determination of use specifications.

4. Preparation of management plans.

5. Training of technical field staff and local persons.

6. Development of interpretive and educational programmes.

7. Planning and layout of visitor facilities, trails.

OUTPUTS

1. Antigua and Barbuda national parks system.

2. Improved environmental management and monitoring capability.

3. Increased number of visitors and national environmental awareness.

4. Increased revenues and linkages with tourism.

5. Data bank of natural resources.

6. Guidelines for resource management and development.

INPUTS

Equipment and materials

Personnel

1 x 4wd station wagon

Project Manager

1 x 4wd pick-up

Parks Planner

1 x 15 foot boat w. motor

Terrestrial Biologist

1 x rubber dinghy w. motor

Marine Biologist

Sampling aids, etc

Fisheries Officer

2 x portable radios

Forestry Assistant


Secretary


Game wardens

NATIONAL LEAD IMPLEMENTING AGENCY;

National Parks Authority in cooperation with Forestry and Fisheries Division, and EAG.

LINKAGES WITH OTHER PROJECTS:

NFAP 1.0 (Country Capacity Project)

OBSERVATIONS:

This project should be coordinated with similar projects in the Caribbean and Central American region.

Project Budget

Table 16. Personnel with Cost Requirements 4

PERSONNEL

MAN MONTHS

FOREIGN COSTS
(US $$)

LOCAL COSTS
(EC $$)

Project Manager

36

300,000


Parks Planner

6

45,000


Terrestrial Biologist

24


50,000

Fisheries Officer

36


75,000

Forestry Assistant

36


40,000

Game Wardens (3)

108


160,000

Secretary

36


48,000

SUB-TOTAL

282

345,000

373,000

4 Project 3 with priority 3 rating.

Table 17 Equipment with Cost Requirements

EQUIPMENT

FOREIGN COSTS
(US $$)

4 wd Vehicles (3)

70,000

Boats & Engines (2)

23,000

Portable Radios (2)

2,000

Sampling Gear

5,000

SUB-TOTAL

100,000

Table 18. Practical Aspects with Associated Costs

PRACTICAL ASPECTS

FOREIGN COSTS
(US $$)

LOCAL COSTS
(EC $$)

Training

10,000


Operating Expenses


180,000

SUB-TOTAL

10,000

180,000

Table 19. Total Budget

BUDGET ITEM

FOREIGN COSTS
(US $$)

LOCAL COSTS
(EC $$)

PERSONNEL

345,000

373,000

EQUIPMENT

100,000


PRACTICAL ASPECTS

10,000

180,000

TOTAL BUDGET

455,000

553,000


Previous Page Top of Page Next Page