10 - OTHER FACILITIES OF THE BEYMELEK CENTRE

When the consultant left, the Beymelek Centre presented the following situation:

  1. Seawater intake: same as 1993–4; still out of order because clogged by sand; main breackwater damaged by storms; restoration works to be started in summer 1995
  2. Pump station: same as 1993–4; not finished and not working
  3. Hatchery: same as 1993–4; completed and working
  4. Resevoir pond: same as 1993–4; completed and working
  5. Guest house: same as 1993–4; completed and working
  6. Training/congress centre: completed, but not yet furnished
  7. Lodgments for trainnees/guests (2nd): same as 1993–4; completed, but not yet furnished
  8. Workshops and storage rooms: completed and working
  9. Concrete raceways: same as 1993–4; 8 pre-growing and 4 on-growing tanks completed, but not working because the pump station is out of order
  10. Earth ponds: same as 1993–4; to be realized
  11. Staff lodgments: 4 new apartment blocks realized and in use.